PMP formulas cheat sheet, with worked examples

The PMP formulas you need fall into five groups: earned value (CV, SV, CPI, SPI, EAC, ETC, VAC and TCPI), three-point estimating (PERT and triangular), schedule float, communication channels, and the value and risk measures (EMV, NPV, payback and benefit-cost ratio). Each is simple arithmetic; what the exam tests is reading the result and choosing the right action, because most PMP questions are situational. Below is every formula with a worked example and what the answer tells a project manager to do.

Earned value: the four inputs

Earned value management compares the value of work completed with what it cost and with what was planned. Every earned value formula is built from four numbers. Get these right and the rest is substitution.

  • Budget at completion (BAC): the total approved budget for the work.
  • Planned value (PV): the budgeted cost of the work scheduled to be done by now.
  • Earned value (EV): the budgeted cost of the work actually done by now.
  • Actual cost (AC): what the work done by now really cost.

Variances and performance indexes

Variances give the gap in money; indexes give efficiency as a ratio. Negative variances and indexes below 1.0 are bad news. Worked example used in this section and the next: BAC $400,000, PV $200,000, EV $180,000, AC $225,000.

  • Cost variance: CV = EV − AC. Here $180,000 − $225,000 = −$45,000, so the work done cost $45,000 more than it was worth.
  • Schedule variance: SV = EV − PV. Here $180,000 − $200,000 = −$20,000 of work behind plan.
  • Cost performance index: CPI = EV ÷ AC. Here 180,000 ÷ 225,000 = 0.8: each dollar spent is buying 80 cents of planned work.
  • Schedule performance index: SPI = EV ÷ PV. Here 180,000 ÷ 200,000 = 0.9: work is progressing at 90% of the planned rate.

Forecasting the final cost: EAC, ETC, VAC and TCPI

The estimate at completion has several formulas, and the exam expects you to pick the one that fits why the variance happened. Ask whether the cause will continue, was a one-off, or shows the estimates were wrong.

  • Cause will continue (typical variance): EAC = BAC ÷ CPI. Here 400,000 ÷ 0.8 = $500,000.
  • One-off cause, rest runs to plan (atypical): EAC = AC + (BAC − EV). Here 225,000 + 220,000 = $445,000.
  • Both cost and schedule performance will shape the rest: EAC = AC + (BAC − EV) ÷ (CPI × SPI). Here 225,000 + 220,000 ÷ 0.72 ≈ $530,600.
  • Original estimates fundamentally flawed: EAC = AC + a new bottom-up estimate of the remaining work.
  • Estimate to complete: ETC = EAC − AC. With the typical EAC, 500,000 − 225,000 = $275,000 still needed.
  • Variance at completion: VAC = BAC − EAC. With the typical EAC, 400,000 − 500,000 = −$100,000: expect to finish $100,000 over budget.
  • To-complete performance index to hit BAC: TCPI = (BAC − EV) ÷ (BAC − AC). Here 220,000 ÷ 175,000 ≈ 1.26. To hit an approved EAC instead, divide by (EAC − AC).

What the earned value answers tell you to do

A TCPI well above the current CPI means the original budget is out of reach unless something changes: in the example, work running at 0.8 would have to jump to about 1.26. The project manager does not hide that or push the team to work faster. They report the forecast honestly, analyse the cause, and take the options (more funding, reduced scope, a corrective action) through governance and change control.

Read SPI with care late in a project: because EV can never exceed BAC, SPI drifts back towards 1.0 as work finishes, even on a project that will finish late. The schedule itself, not SPI alone, says whether the end date is at risk.

Three-point estimating: PERT and triangular

Three-point estimates combine an optimistic (O), most likely (M) and pessimistic (P) value. Read which distribution the question names, because the two formulas give different answers. Worked example: O = 4 days, M = 7 days, P = 16 days.

  • Beta (PERT) estimate: (O + 4M + P) ÷ 6. Here (4 + 28 + 16) ÷ 6 = 8 days.
  • Triangular estimate: (O + M + P) ÷ 3. Here (4 + 7 + 16) ÷ 3 = 9 days.
  • Standard deviation of a beta estimate: (P − O) ÷ 6. Here (16 − 4) ÷ 6 = 2 days; a wider spread means a less certain estimate.

Schedule float

Total float is how long an activity can slip without delaying the project finish; free float is how long it can slip without delaying the early start of any successor. Free float is never larger than total float, and activities on the critical path normally have zero total float.

  • Total float = late start − early start (or late finish − early finish). An activity with early start day 5 and late start day 9 has 4 days of total float.
  • Free float (finish-to-start, no lag) = earliest early start of the successors − the activity’s early finish.
  • A delay within free float affects nothing else; beyond free float but within total float it pushes successors without moving the finish date; beyond total float it moves the finish date by the excess.

Communication channels

The number of communication channels is n(n − 1) ÷ 2, where n counts everyone involved, including the project manager. It grows much faster than the head count: a team of 8 has 8 × 7 ÷ 2 = 28 channels, and growing to 12 gives 12 × 11 ÷ 2 = 66, so adding four people adds 38 channels. When a question asks how many channels were added, work out both totals and subtract.

Risk and value: EMV, NPV, payback and BCR

Expected monetary value is probability × impact, with threats negative and opportunities positive. A threat with a 30% chance of costing $50,000 has an EMV of −$15,000; an opportunity with a 20% chance of saving $40,000 has an EMV of +$8,000. When comparing options, add each option’s EMV to its base cost and choose the lower expected cost.

For choosing between projects or options, the exam asks you to apply a decision rule rather than compute a discounted cash flow from scratch:

  • Net present value (NPV): higher is better, and a negative NPV destroys value. It is the standard rule for choosing between mutually exclusive options.
  • Payback period: shorter is better, but it ignores everything after payback and the time value of money; it decides only when the organisation makes cash recovery the constraint.
  • Benefit-cost ratio (BCR): above 1 is worthwhile and higher is better, but it says nothing about the size of the project.
  • Internal rate of return (IRR): higher is better; compare it with the organisation’s required rate.

Agile cost: burn rate

Agile teams cost roughly the same each iteration, so remaining cost is the burn rate × the iterations left. A team costing $40,000 per iteration with five iterations remaining needs $200,000 more. Iterations already finished are sunk and play no part in the forecast; with a fixed budget, the burn rate sets how many iterations it buys and scope is what flexes.

Start studying for PMP — free
Revision notes, explained practice questions and timed mock exams.

Try it with your own numbers

  • Earned value calculator Enter BAC, PV, EV and AC to get every earned value measure and what it means.
  • PERT calculator Enter three estimates to get the PERT and triangular estimates and confidence ranges.

Plan your prep

Questions, answered

Earned value (CV, SV, CPI, SPI, EAC, ETC, VAC and TCPI), three-point estimating (PERT and triangular), total and free float, communication channels n(n − 1) ÷ 2, and expected monetary value, plus the decision rules for NPV, payback, benefit-cost ratio and IRR.