Earned value calculator
Enter the budget at completion, planned value, earned value and actual cost to get every earned value measure: CV, SV, CPI, SPI, the three EAC formulas, ETC, VAC and TCPI. It also says what the numbers mean for the project, which is what PMP questions actually ask.
| Measure | Formula | Result |
|---|---|---|
| Cost variance (CV) | EV − AC | −$45,000 |
| Schedule variance (SV) | EV − PV | −$20,000 |
| Cost performance index (CPI) | EV ÷ AC | 0.80 |
| Schedule performance index (SPI) | EV ÷ PV | 0.90 |
| EAC, cause will continue | BAC ÷ CPI | $500,000 |
| EAC, one-off cause | AC + (BAC − EV) | $445,000 |
| EAC, cost and schedule both matter | AC + (BAC − EV) ÷ (CPI × SPI) | $530,556 |
| Estimate to complete (ETC) | EAC − AC (typical EAC) | $275,000 |
| Variance at completion (VAC) | BAC − EAC (typical EAC) | −$100,000 |
| TCPI to finish on BAC | (BAC − EV) ÷ (BAC − AC) | 1.26 |
What this tells you
- Over budget: CPI 0.80 means each dollar spent is buying 80 cents of planned work (CV −$45,000).
- Behind schedule: SPI 0.90, work is progressing at 90% of the planned rate (SV −$20,000).
- Finishing on budget would need a TCPI of 1.26 against a current CPI of 0.80: unrealistic unless something changes. Report the forecast honestly and take the options (funding, scope, corrective action) through change control.