Earned value calculator

Enter the budget at completion, planned value, earned value and actual cost to get every earned value measure: CV, SV, CPI, SPI, the three EAC formulas, ETC, VAC and TCPI. It also says what the numbers mean for the project, which is what PMP questions actually ask.

MeasureFormulaResult
Cost variance (CV)EV − AC−$45,000
Schedule variance (SV)EV − PV−$20,000
Cost performance index (CPI)EV ÷ AC0.80
Schedule performance index (SPI)EV ÷ PV0.90
EAC, cause will continueBAC ÷ CPI$500,000
EAC, one-off causeAC + (BAC − EV)$445,000
EAC, cost and schedule both matterAC + (BAC − EV) ÷ (CPI × SPI)$530,556
Estimate to complete (ETC)EAC − AC (typical EAC)$275,000
Variance at completion (VAC)BAC − EAC (typical EAC)−$100,000
TCPI to finish on BAC(BAC − EV) ÷ (BAC − AC)1.26

What this tells you

  • Over budget: CPI 0.80 means each dollar spent is buying 80 cents of planned work (CV −$45,000).
  • Behind schedule: SPI 0.90, work is progressing at 90% of the planned rate (SV −$20,000).
  • Finishing on budget would need a TCPI of 1.26 against a current CPI of 0.80: unrealistic unless something changes. Report the forecast honestly and take the options (funding, scope, corrective action) through change control.

Learn the method

Earned value: your questions

A cost performance index below 1.0 means the project is over budget for the work done: with a CPI of 0.8, every dollar spent is buying 80 cents of planned work. Above 1.0 means under budget.