PERT calculator

Enter optimistic, most likely and pessimistic estimates for an activity to get the PERT (beta) estimate, the triangular estimate, the standard deviation and the ranges you can expect the result to fall in.

MeasureFormulaResult
PERT (beta) estimate(O + 4M + P) ÷ 68
Triangular estimate(O + M + P) ÷ 39
Standard deviation (σ)(P − O) ÷ 62
Varianceσ²4
Range, ±1σ (≈68%)beta ± 1 × σ6 – 10
Range, ±2σ (≈95%)beta ± 2 × σ4 – 12
Range, ±3σ (≈99.7%)beta ± 3 × σ2 – 14

The beta estimate weights the most likely value four times; the triangular estimate gives all three equal weight. Use the one the question names. The confidence ranges assume a roughly normal spread around the beta estimate.

Learn the method

PERT estimates: your questions

The PERT (beta) estimate is (O + 4M + P) ÷ 6, where O is the optimistic, M the most likely and P the pessimistic estimate. It weights the most likely value four times as heavily as either extreme.