PMI-ACP practice

PMI-ACP sample questions — 25 answered and explained

25 PMI-ACP sample questions written to the official PMI Agile Certified Practitioner (PMI-ACP) exam guide, grouped by exam domain and weighted like the real exam. Each shows the correct answer, why every other option is wrong, and the lesson that teaches it. None of them repeat the examples on the other PMI-ACP practice pages.

On this page
25
answers included
Full bank
952
on the practice page
Domains
4
weighted like the exam
Free, no account
5/day
a free account allows 10 a day

Domain 1: Mindset

28% of the PMI-ACP exam, so 7 of the 25 questions on this page.

Question 1Mindset

After a two-day spike, a developer reports that the third-party API can do what the story needs, but the spike code is messy and untested. The product owner suggests shipping the spike code to save time. What should the agile practitioner recommend?

Choose one.

  • a
    Ship the spike code and add a backlog item to tidy it up later

    This ships work that does not meet the definition of done and creates technical debt that may never be repaid.

  • b
    Extend the spike timebox until the code is ready for production

    A spike is timeboxed to answer one question, which it has done. Turning it into delivery work blurs the two.

  • c
    Ask the developer to finish testing the spike code this evening

    Overtime is unsustainable, and testing messy exploratory code does not make it fit for production.

  • d
    Use the learning and build the story to the definition of done Correct

    A spike's output is knowledge. The story should be built properly, meeting the definition of done, using what the spike revealed.

The concept

Spikes produce knowledge, not shippable code; the real work is then built to the definition of done.

Why that’s the answer

The spike has answered its question (the API works). Its code was written to learn fast, not to last. The story should now be built to the definition of done. Shipping or extending the spike, or patching it with overtime, trades long-term quality for a short-term saving.

How to reason it out
  1. Confirm the spike answered its question.
  2. Recall that spike code is throwaway by intent.
  3. Apply the definition of done to the real story.
  4. Reject options that ship or stretch exploratory code.

Exam tip: Keep the spike's lesson; rebuild its code to the definition of done.

PMI-ACP Experiment Early: MVPs, Spikes, Hypotheses and a Culture of Innovation — the lesson that teaches this.

Question 2Mindset

A spike was timeboxed at three days to find out whether an open-source search engine can index the product catalogue fast enough. At the end of the timebox the results are inconclusive. The developer asks for 'a few more days'. What should happen next?

Choose one.

  • a
    Let the developer continue until the answer becomes clear

    An open-ended extension removes the timebox that keeps exploratory work from silently consuming capacity.

  • b
    Treat the engine as unsuitable and choose a commercial product

    An inconclusive result is not a failure; deciding against the engine ignores what was learned.

  • c
    Start building the search story with the engine as planned

    Starting delivery while the key question is still open carries the risk the spike was meant to reduce.

  • d
    Decide next steps with the product owner using the findings Correct

    The timebox has ended, so the team and product owner decide whether the remaining uncertainty is worth another timeboxed investment.

The concept

A timebox forces a decision point: when it ends, the team and product owner act on what was learned rather than extending by default.

Why that’s the answer

The timebox exists so the product owner can weigh further investment against other work. An inconclusive spike goes back to that decision — another short timebox, a different approach or a different option. Continuing indefinitely, abandoning the engine, or building anyway each skip the decision.

How to reason it out
  1. Notice the timebox has ended.
  2. Recognise the product owner decides how capacity is spent.
  3. Treat 'inconclusive' as information, not success or failure.
  4. Choose the option that makes a deliberate decision.

Exam tip: When a timebox ends, decide; don't drift.

PMI-ACP Experiment Early: MVPs, Spikes, Hypotheses and a Culture of Innovation — the lesson that teaches this.

Question 3Mindset

A product owner wants to validate that small retailers need an inventory forecasting feature before the team builds it out. Which TWO pieces of evidence best validate the market need? (Select TWO.)

Choose TWO.

  • a
    Retailers in a survey say they would use forecasts weekly

    Stated intent in a survey often differs from what people actually do.

  • b
    Sales staff report that retailers often ask about forecasts

    Second-hand anecdotes suggest interest but are not evidence of use or willingness to pay.

  • c
    Pilot retailers praise the forecasts at a review session

    Praise is opinion, even from target users; it does not show they will use the forecasts or pay for them.

  • d
    Retailers in the pilot use forecasts to place real orders Correct

    Real use of the increment in their own work is behavioural evidence that the feature meets a need.

  • e
    Pilot retailers pay for forecasting once the trial ends Correct

    Paying once the free trial ends is behaviour, not a promise, and shows the need is worth money to them.

The concept

Market need is validated by what target customers do with an increment — use it, pay for it, come back — not by what they or others say.

Why that’s the answer

Using forecasts to place real orders and paying after the trial are both behaviour from the target customers. Praise at a review session and survey answers are opinions, and sales anecdotes are second-hand, so none of them shows the need is real.

How to reason it out
  1. Identify the target users: small retailers.
  2. Separate behaviour (use, payment) from opinion (praise, surveys, anecdotes).
  3. Prefer first-hand evidence from the users themselves.
  4. Choose the behavioural evidence from target users.

Exam tip: Behaviour beats opinion when validating market need.

PMI-ACP Experiment Early: MVPs, Spikes, Hypotheses and a Culture of Innovation — the lesson that teaches this.

Question 4Mindset

A team has two candidate designs for its pricing page and wants evidence of which one leads more visitors to start a free trial. The site has steady, high traffic. Which approach gives the most reliable answer?

Choose one.

  • a
    Release one design this month and the other one next month

    Sequential releases mix the design's effect with seasonal and campaign changes between the two months.

  • b
    Show each design to a random half of visitors and compare Correct

    Running both designs at the same time on randomly split traffic isolates the effect of the design from timing and audience changes.

  • c
    Ask a focus group of customers which design they prefer

    Preference in a focus group is an opinion and may not match what visitors do on the page.

  • d
    Have the UX lead pick a design using established heuristics

    Expert judgment is useful input but produces no evidence of how visitors actually respond.

The concept

A randomized controlled comparison (A/B test) is the most reliable way to attribute a difference in behaviour to a change.

Why that’s the answer

With high traffic, the team can split visitors randomly and measure trial starts for both designs at once. Sequential releases confound the result with time, while a focus group and an expert's choice rely on opinion rather than observed behaviour.

How to reason it out
  1. Note the goal: evidence about visitor behaviour.
  2. Note the enabler: enough traffic to split.
  3. Prefer simultaneous, random assignment over sequential tests.
  4. Reject options based on opinion.

Exam tip: Split traffic randomly and run variants side by side to learn which one works.

PMI-ACP Experiment Early: MVPs, Spikes, Hypotheses and a Culture of Innovation — the lesson that teaches this.

Question 5Mindset

A scrum master notices the team only proposes 'safe' improvements. Any experiment, however small, needs sign-off from a change board that meets once a month, so ideas wait weeks. What should the scrum master do?

Choose one.

  • a
    Agree a fast path with leaders for small experiments Correct

    A lightweight route for low-risk experiments removes the delay that discourages the team, while keeping larger changes governed.

  • b
    Batch the team's ideas for the next monthly board meeting

    Batching keeps the monthly delay that is causing the problem.

  • c
    Coach the team to write better board proposals

    Better proposals still wait for the monthly meeting, so the barrier to experimenting remains.

  • d
    Run the experiments quietly and tell the board afterward

    Bypassing governance hides work and damages trust; the barrier should be changed openly.

The concept

Leaders create an environment to innovate by removing systemic barriers — such as heavy approval for small experiments — rather than working around them.

Why that’s the answer

The cause of the 'safe' ideas is a monthly approval cycle for every experiment. Negotiating a fast path for small, contained experiments fixes the cause transparently. Batching or better proposals keep the delay, and running experiments secretly undermines trust.

How to reason it out
  1. Identify the cause: approval delay on every experiment.
  2. Look for an option that changes the system, not the team's behaviour.
  3. Keep governance for larger changes.
  4. Reject options that hide work from governance.

Exam tip: Lower the cost of trying small things; keep heavy gates for big ones.

PMI-ACP Experiment Early: MVPs, Spikes, Hypotheses and a Culture of Innovation — the lesson that teaches this.

Question 6Mindset

Developers on a team keep running exploratory experiments 'on the side'. The product owner is surprised when committed stories slip and says she did not know the experiments were happening. How should the team handle experiments in future?

Choose one.

  • a
    Limit them to developers who finish their stories early

    This keeps experiments informal and invisible, and makes them depend on spare time rather than value.

  • b
    Track them in a separate list shared with the product owner

    Sharing a side list gives the product owner sight of it but not the ordering decision, so experiments still bypass the backlog trade-off.

  • c
    Stop them until the team reliably meets its forecast

    Stopping experiments removes early learning instead of fixing the visibility problem.

  • d
    Put them in the backlog for the product owner to order Correct

    Experiments in the backlog are visible and compete openly for capacity, so the product owner can weigh them against other work.

The concept

Experiments and spikes are real work: they belong in the backlog where the product owner can see and order them against other items.

Why that’s the answer

The problem is hidden work competing with committed stories. Putting experiments in the backlog makes the trade-off visible and lets the product owner order them. The other options keep the work hidden, put it under someone without that authority, or drop early learning.

How to reason it out
  1. Identify the problem: invisible work using capacity.
  2. Recall who orders the backlog: the product owner.
  3. Make the experiments visible where trade-offs are made.
  4. Reject options that hide or abandon them.

Exam tip: If it uses team capacity, it belongs in the backlog.

PMI-ACP Experiment Early: MVPs, Spikes, Hypotheses and a Culture of Innovation — the lesson that teaches this.

Question 7Mindset

Early in a project, the team is unsure which of two data storage approaches will meet its performance needs. Both look plausible, much of the design depends on the choice, and switching later would be expensive. What should the team do?

Choose one.

  • a
    Test both approaches with small experiments, then commit Correct

    Small experiments on both options produce evidence for a choice that is costly to reverse, while the cost of learning is still low.

  • b
    Pick the approach the team knows best and start building

    Familiarity is not evidence of performance, and committing now risks an expensive switch later.

  • c
    Pause the design work until a full performance study is done

    A long study delays all value; small experiments answer the question sooner.

  • d
    Ask the architect to choose one now to avoid later rework

    Choosing without evidence does not avoid rework; it risks the most expensive kind.

The concept

When an early decision is uncertain and costly to reverse, keep options open and use small experiments to decide with evidence.

Why that’s the answer

Two plausible approaches, high reversal cost and little evidence: running small experiments on both is the cheapest way to make a sound choice early. Picking by familiarity or authority commits without evidence, and pausing all work for a full study is slow.

How to reason it out
  1. Note the uncertainty and the high cost of switching.
  2. Prefer cheap evidence before an expensive commitment.
  3. Keep both options alive briefly.
  4. Decide when the experiments report back.

Exam tip: For costly, uncertain decisions, experiment on the options before committing.

PMI-ACP Experiment Early: MVPs, Spikes, Hypotheses and a Culture of Innovation — the lesson that teaches this.

Domain 2: Leadership

25% of the PMI-ACP exam, so 6 of the 25 questions on this page.

Question 8Leadership

On a fully remote team, a developer who usually keeps the camera on and talks freely has had it off for three days and answers chat only with one-word replies. When the scrum master asks in stand-up whether all is well, the developer says 'fine' and moves on. What should the scrum master do?

Choose one.

  • a
    Treat the change as a signal and follow up one to one Correct

    On remote teams, a change in camera use and chat tone is the non-verbal cue available. Paired with a brief 'fine', it is worth a private, low-pressure check-in.

  • b
    Accept the 'fine' the developer gave when asked in stand-up

    The words and the behaviour disagree. Taking 'fine' at face value ignores the change that prompted the question.

  • c
    Ask the team to keep cameras on so cues stay visible

    A camera rule addresses the scrum master's visibility, not the developer's situation, and can feel like surveillance to someone already withdrawn.

  • d
    Raise remote engagement as a retrospective topic

    A group discussion of engagement may be useful later, but it avoids the individual signal and may put the developer on the spot.

The concept

Remote teams show non-verbal cues through camera use, response tone, latency and silence; a change from a person's norm matters more than the cue itself.

Why that’s the answer

Two facts combine. First, the useful cue is the change from the developer's usual behaviour, which on a remote team shows in camera use and chat tone. Second, a public question that gets a closed answer has not resolved the signal, so the right move is a private follow-up rather than accepting the words. Mandating cameras and group discussions address visibility in general and not this person.

How to reason it out
  1. Identify the remote equivalents of body language: camera, tone, response style.
  2. Compare against the person's normal behaviour.
  3. Note that the public 'fine' contradicts the behaviour.
  4. Follow up privately rather than accepting or broadcasting it.

Exam tip: On remote teams, a change in how someone shows up is the cue; check privately, not in the group.

PMI-ACP Empower Teams: Trust, Motivation, Coaching vs Mentoring vs Training, Emotional Intelligence and Self-Assessment — the lesson that teaches this.

Question 9Leadership

A team completes an anonymous health-check self-assessment scored 1 to 5. Most areas average about 4, and 'Delivering value' averages 3.5, but four members scored it 5 and four scored it 2. What should the agile practitioner do with this result?

Choose one.

  • a
    Treat value delivery as healthy since its average is acceptable

    An acceptable average hides a polarised result. Four people rating it 2 is a signal the average conceals.

  • b
    Make delivering value, the lowest area, next iteration's improvement goal

    Targeting the lowest average looks sensible, but it assumes the whole team sees a problem. Half the team rated value 5, so an improvement goal set now skips understanding why views differ.

  • c
    Facilitate a discussion of why views on value differ so much Correct

    The split means half the team sees a serious problem the other half does not. Exploring that gap is where the useful information is.

  • d
    Ask the product owner which half of the team has it right

    Having one person rule on the scores misses the point of a self-assessment and loses the team's own understanding of the gap.

The concept

Self-assessment output should be read for spread and patterns, not just averages; strong disagreement between members is itself a finding.

Why that’s the answer

An average of 3.5 looks only slightly below the rest, but it hides a bimodal split. When half the team rates something 5 and half rates it 2, members are experiencing or defining the area differently, and that is what the team needs to talk about. Treating the average as healthy, or setting an improvement goal for the lowest area straight away, acts on a number the team does not agree on; asking the product owner to rule loses the team's own understanding.

How to reason it out
  1. Look beyond averages to the distribution of scores.
  2. Recognise a split as different perceptions within the team.
  3. Use the result to start a team conversation, not to reach a verdict.
  4. Let the team surface what lies behind the gap.

Exam tip: In self-assessments, a wide spread of scores can matter more than a low average.

PMI-ACP Empower Teams: Trust, Motivation, Coaching vs Mentoring vs Training, Emotional Intelligence and Self-Assessment — the lesson that teaches this.

Question 10Leadership

Teams in a department complete a self-assessment of agile practices each quarter. A director proposes ranking teams by their scores and linking the top scores to a team bonus. What should the agile practitioner recommend?

Choose one.

  • a
    Normalise scores across teams before ranking them

    Normalisation tidies the numbers but keeps the ranking and the bonus, which give teams a reason to inflate their own ratings.

  • b
    Keep the scores for each team's own improvement planning Correct

    Self-assessments work because teams rate themselves honestly. Keeping them as a team improvement tool protects that honesty.

  • c
    Have an external assessor confirm scores before ranking

    Validation tries to fix the inflation the bonus creates, but it turns a self-assessment into an audit and still ranks teams.

  • d
    Rank the teams but keep the individual scores confidential

    Hiding the detail does not remove the incentive. Teams would still rate themselves to win the ranking.

The concept

Team self-assessments are improvement tools for the team; tying them to rankings or rewards distorts the scores.

Why that’s the answer

Once scores affect bonuses or rankings, teams have every reason to score themselves high, and the tool stops telling anyone the truth. Normalising, validating or anonymising the scores all keep the comparison that causes the problem. The practitioner should keep the results with the teams, as input for their own improvement.

How to reason it out
  1. Identify who the self-assessment is for: the team.
  2. Predict what a reward does to self-reported scores.
  3. Reject fixes that keep the ranking.
  4. Keep the tool as input to the team's improvement.

Exam tip: Self-assessment scores stay honest only while they are used for the team's own improvement.

PMI-ACP Empower Teams: Trust, Motivation, Coaching vs Mentoring vs Training, Emotional Intelligence and Self-Assessment — the lesson that teaches this.

Question 11Leadership

Six months of a team's quarterly self-assessments show technical practice scores rising steadily, while 'collaboration with the product owner' fell from 4 to 2 in the latest round. In the review meeting, the team proposes writing an improvement action for every area scored below 3. What should the agile practitioner suggest?

Choose one.

  • a
    Write actions for each area that scored below 3

    Spreading effort over every low area dilutes it, and writing actions before understanding the sharp drop risks fixing symptoms.

  • b
    Coach the product owner on collaboration techniques

    This assumes the product owner is the cause. The score describes a relationship, so the team needs to understand it together first.

  • c
    Repeat the assessment next month to confirm the drop

    Waiting delays action on a clear and sharp change. One more data point adds little compared with talking about what happened.

  • d
    Explore the drop with the team and the product owner Correct

    A sharp fall in one area is the strongest signal in the data. Understanding its cause with the people involved comes before choosing actions.

The concept

Interpreting self-assessment output means looking at trends over time and exploring significant changes with the team before acting.

Why that’s the answer

Two facts decide this. Trends matter: a fall from 4 to 2 in one quarter is a significant change, unlike a steady pattern. And self-assessment results should start a conversation, not prescribe a fix, so the team and the product owner need to explore why collaboration fell. Actions for every low area lack focus; coaching only the product owner assumes the cause; re-running the survey delays a clear signal.

How to reason it out
  1. Compare the latest scores with the trend, not just with a threshold.
  2. Spot the sharpest change as the most important signal.
  3. Explore its cause with everyone involved before choosing actions.
  4. Keep improvement focused rather than spread across every area.

Exam tip: Treat a sharp change in a self-assessment trend as a question to explore together, not a verdict.

PMI-ACP Empower Teams: Trust, Motivation, Coaching vs Mentoring vs Training, Emotional Intelligence and Self-Assessment — the lesson that teaches this.

Question 12Leadership

In planning, each story is assigned to one developer. Two days before the iteration ends, three stories are unfinished while two developers who finished their own stories wait for new work, saying 'those aren't mine'. What should the agile practitioner do?

Choose one.

  • a
    Reassign the unfinished stories to the developers who are free

    This may help this iteration, but the practitioner is directing the work, and the habit of individual ownership stays as it was.

  • b
    Add each developer's completion rate to the team dashboard

    Individual metrics strengthen the 'my stories' mindset that caused the problem.

  • c
    Coach the team to own the iteration goal and swarm on stories Correct

    Making the goal the team's shared responsibility lets idle members help finish open stories, and it addresses why they stopped.

  • d
    Ask the product owner to remove the three unfinished stories

    Cutting scope hides the symptom while capacity sits idle, and the team learns nothing about working toward a shared goal.

The concept

Collective ownership means the team commits to and is accountable for a shared goal, not individuals for their own tasks.

Why that’s the answer

The cause is individual ownership created by assigning stories in planning. The practitioner should help the team see the iteration goal as theirs together and work as a group on open stories. Reassigning work is the practitioner deciding for the team; individual metrics reinforce the problem; cutting scope leaves free capacity unused.

How to reason it out
  1. Find the root cause: work was owned by individuals, not the team.
  2. Prefer an action that changes how the team sees ownership.
  3. Avoid the practitioner directing the work.
  4. Avoid measures that reinforce individual ownership.

Exam tip: Agile teams succeed or fail together: frame goals as the team's and let members swarm.

PMI-ACP Empower Teams: Trust, Motivation, Coaching vs Mentoring vs Training, Emotional Intelligence and Self-Assessment — the lesson that teaches this.

Question 13Leadership

A manager plans to pay individual bonuses based on the story points each developer completes, to reward high performers on an agile team. The agile practitioner is asked for an alternative that still recognises good work. What should the practitioner recommend?

Choose one.

  • a
    Base the bonuses on whole-team velocity instead

    This moves to team level, but it makes velocity a target. Teams then inflate estimates, and velocity stops being useful for planning.

  • b
    Recognise the team for outcomes it delivers together Correct

    Team-level recognition for delivered outcomes rewards good work while keeping members focused on the shared goal.

  • c
    Keep individual bonuses but weight them by complexity

    Weighting changes the formula, not the incentive. Developers still compete for points instead of helping each other.

  • d
    Base individual bonuses on peer feedback scores

    Peer input feels collaborative, but tying individual pay to it turns feedback into a popularity contest and keeps the focus on individuals.

The concept

Collective ownership is undermined by individual output rewards; using velocity as a performance target makes it unreliable as a planning measure.

Why that’s the answer

Two facts combine. Individual rewards for story points push developers to optimise their own numbers rather than the team's goal. Moving the same reward to team velocity looks like a fix, but rewarding velocity invites estimate inflation. Recognising the team for outcomes it delivers keeps both collective ownership and honest estimation. Complexity weighting and peer-rated bonuses keep the individual competition.

How to reason it out
  1. Ask what each incentive pushes people to optimise.
  2. Spot rewards that focus on individuals instead of the team.
  3. Spot rewards that turn a planning measure into a target.
  4. Choose recognition tied to shared outcomes.

Exam tip: Reward the team for outcomes, never individuals for points, and never turn velocity into a target.

PMI-ACP Empower Teams: Trust, Motivation, Coaching vs Mentoring vs Training, Emotional Intelligence and Self-Assessment — the lesson that teaches this.

Domain 3: Product

19% of the PMI-ACP exam, so 5 of the 25 questions on this page.

Question 14Product

Two senior stakeholders each insist that their feature must be first in the next release, and both escalate to the product owner, who asks the scrum master to choose. The features serve different customer groups. What should the scrum master do?

Choose one.

  • a
    Facilitate a joint value comparison of the two features Correct

    The product owner decides the order together with stakeholders. A facilitated comparison of value helps them reach an informed order, with the decision staying with the product owner.

  • b
    Rank the two features by their story point estimates

    Size alone ignores value. Ordering the smaller feature first may not serve the customers or the business best.

  • c
    Ask the sponsor to decide between the two features

    Escalating takes the ordering away from the product owner and stakeholders before they have compared value together.

  • d
    Let the development team choose which feature comes first

    The team informs ordering with cost and risk, but value trade-offs between customer groups are the product owner's call with stakeholders.

The concept

Backlog items are prioritized by the product owner with customers and stakeholders, using value. A scrum master facilitates; they do not decide the order.

Why that’s the answer

The scrum master's role is to facilitate the product owner and stakeholders in comparing value, not to choose. Ranking by size ignores value, escalating to the sponsor skips the collaboration, and the team does not own value decisions between customer groups.

How to reason it out
  1. Identify who owns the order: the product owner, with stakeholders.
  2. Identify the scrum master's role: facilitation.
  3. Pick the option that brings the parties together around value.

Exam tip: The product owner orders the backlog with stakeholders; the scrum master facilitates, not decides.

PMI-ACP Product Backlog Refinement: Clarifying, Prioritizing, Splitting and Sizing Backlog Items — the lesson that teaches this.

Question 15Product

A team splits a large 'online checkout' item into three stories: build the database tables, build the payment API, and build the checkout screens. After two iterations nothing can be shown to customers because no story works without the others. How should the team split such items instead?

Choose one.

  • a
    By the architectural layer each developer owns

    Splitting by layer is what the team already did. Each layer story is unusable until the others are finished.

  • b
    By the technical tasks each story requires

    Tasks belong inside a story. Turning them into backlog items repeats the problem of work that delivers no value on its own.

  • c
    By merging them back into one epic-sized story

    Recombining removes the coupling but leaves an item too large to finish and show within an iteration.

  • d
    By the steps a buyer completes, end to end Correct

    Vertical slices cut through every layer to deliver a thin piece of working behaviour, such as paying by card, that can be demonstrated and gets feedback.

The concept

Backlog items are decomposed into vertical slices: each one crosses every layer and delivers a small, usable behaviour.

Why that’s the answer

Horizontal (layer) splits deliver nothing usable until all are finished, which is the symptom described. Splitting by the buyer's workflow steps gives demonstrable value each iteration. Technical tasks are a sub-level of a story, and merging back loses the benefit of decomposition.

How to reason it out
  1. Spot the symptom: no story works without the others.
  2. Recognise a horizontal (layer) split.
  3. Choose a split that delivers working behaviour per story.

Exam tip: Slice vertically, through every layer, so each story works and can be shown.

PMI-ACP Product Backlog Refinement: Clarifying, Prioritizing, Splitting and Sizing Backlog Items — the lesson that teaches this.

Question 16Product

A story 'Customers can manage their subscription' has been sized at 40 points, but the team usually completes about 30 points per iteration. Which TWO splits produce stories that each still deliver value to the customer? (Select TWO.)

Choose TWO.

  • a
    Building the subscription database tables as the first story

    A database-only story is a horizontal slice. Customers cannot use it until other stories are built.

  • b
    Designing the subscription screens as the first story

    Screens without working behaviour deliver nothing a customer can use. It is a layer split.

  • c
    Writing the automated tests for subscriptions as a separate story

    Testing belongs inside each story's definition of done. A test-only story leaves earlier stories untested and adds no customer value.

  • d
    Pausing a subscription as one story, cancelling as another Correct

    Splitting by operation gives two working capabilities a customer can use and the team can demonstrate.

  • e
    Changing plans for monthly customers first, annual customers later Correct

    Splitting by data or customer variation delivers a full plan change to one group first and extends it later.

The concept

Common splitting patterns cut by workflow step or operation, by business rule, and by data or customer variation. Each resulting story keeps value for the user.

Why that’s the answer

Pausing versus cancelling splits by operation, and monthly versus annual splits by variation. Both leave each piece usable. The database, screen and test stories are layer or activity splits that deliver no value on their own.

How to reason it out
  1. Note the need: the story is larger than one iteration.
  2. Test each split: could a customer use the result on its own?
  3. Keep the operation and variation splits; drop the layer and activity splits.

Exam tip: Good splits cut by operation, rule or variation; bad splits cut by layer or activity.

PMI-ACP Product Backlog Refinement: Clarifying, Prioritizing, Splitting and Sizing Backlog Items — the lesson that teaches this.

Question 17Product

During planning poker for a story, five developers reveal 3, 3, 5, 5 and 20 at the same time. What should happen next?

Choose one.

  • a
    The team records the average of the five estimates

    Averaging hides the reason for the 20, which may be a risk the rest of the team missed.

  • b
    The highest and lowest estimators explain their views Correct

    Outliers often know something the others do not. Their explanations are discussed, then the team votes again.

  • c
    The team records the most common estimate and moves on

    Taking the majority skips the conversation that planning poker exists to trigger when estimates differ.

  • d
    The most experienced developer chooses the final estimate

    Letting one person decide loses the collective view and invites anchoring on seniority.

The concept

Planning poker: everyone reveals at once, the outliers explain, the team discusses and re-votes until estimates converge.

Why that’s the answer

A wide spread signals different understandings of the work. The process asks the highest and lowest estimators to explain, then re-votes. Averaging, majority and deferring to seniority all skip the discussion that makes collective estimates reliable.

How to reason it out
  1. Notice the wide spread, with one outlier at 20.
  2. Recall what planning poker does with divergent estimates.
  3. Choose discussion led by the outliers, then a new vote.

Exam tip: In planning poker, divergence is information: hear the outliers, then re-vote.

PMI-ACP Product Backlog Refinement: Clarifying, Prioritizing, Splitting and Sizing Backlog Items — the lesson that teaches this.

Question 18Product

A developer who has just joined the team asks how many hours a 5-point story takes, because his previous team converted points to hours. How should the agile practitioner explain story points?

Choose one.

  • a
    They are a fixed number of team hours set by the team

    Fixing a conversion turns points into disguised hours and loses the benefit of relative sizing.

  • b
    They measure the business value each story will deliver

    Points size the work. Business value is a separate measure used for ordering the backlog.

  • c
    They show size relative to stories the team agreed on Correct

    Story points express the effort, complexity and uncertainty of an item relative to other items, using reference stories the team agreed.

  • d
    They are set by the product owner for each backlog item

    The people who will do the work size it. The product owner clarifies the item but does not estimate it.

The concept

Story points are a relative, unitless measure of effort, complexity and uncertainty, set by the team against reference stories.

Why that’s the answer

A 5-point story is roughly five-thirds the size of a 3-point reference story for that team, whatever the hours. Converting points to hours, treating them as value, or having the product owner set them are common misunderstandings.

How to reason it out
  1. Recall what story points measure.
  2. Recall who sets them and against what reference.
  3. Reject options that fix them to hours, value or the product owner.

Exam tip: Story points are relative size set by the team, not hours and not value.

PMI-ACP Product Backlog Refinement: Clarifying, Prioritizing, Splitting and Sizing Backlog Items — the lesson that teaches this.

Domain 4: Delivery

28% of the PMI-ACP exam, so 7 of the 25 questions on this page.

Question 19Delivery

A team deploys to production every week, but the product owner holds finished features until a quarterly marketing launch, so features wait up to twelve weeks before any customer uses them. Marketing requires that nothing is announced or generally available before the launch date. What should the agile practitioner propose?

Choose one.

  • a
    Enable held features for an invited pilot group via flags Correct

    Feature flags let the code be deployed but switched on only for invited customers, giving real feedback weeks earlier with nothing generally available.

  • b
    Ask marketing to move to a monthly launch cycle instead

    Marketing has set the quarterly launch as a constraint. Asking it to change may fail, and feedback would still wait up to a month.

  • c
    Demonstrate held features to marketing at each review

    Marketing staff are not the end customers. Their opinions do not replace feedback from people using the feature.

  • d
    Release the held features to a staging site for staff testing

    Staff testing in staging finds defects but gives no feedback from customers, which is what the twelve-week wait is delaying.

The concept

Feature flags (toggles) separate deploying code from releasing it to users. Code can sit in production switched off for everyone except a chosen group, so feedback starts before a public launch.

Why that’s the answer

The deciding constraint is "nothing generally available before launch". A flag-controlled pilot satisfies it while giving real customer feedback within a week of deployment. Changing marketing’s cycle ignores the constraint, and demos or staging tests produce internal opinions rather than customer use.

How to reason it out
  1. Note that deployment is already weekly; the delay is in release.
  2. Note the constraint: no general availability before launch.
  3. Find the option that lets a small invited group use the feature now.
  4. Reject options whose feedback comes only from staff.

Exam tip: Deploying is not releasing: flags let a chosen few use finished work long before the public launch.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 20Delivery

A team wants to release to users every week to get feedback sooner. Every release needs a four-day manual regression test, so the team releases only once a month. Which change most directly lets it release weekly without lowering quality?

Choose one.

  • a
    Automate the regression tests and run them on each commit Correct

    Automated regression tests run in minutes on each change, so the product is always checked and ready to release.

  • b
    Limit the manual regression test to the riskiest areas

    This shortens testing by testing less, so defects in other areas become more likely to reach users.

  • c
    Release weekly to a staging site and monthly to users

    Quality is kept, but users still see changes only once a month, so customer feedback arrives no sooner. The goal was weekly releases to users.

  • d
    Add more testers so manual regression takes two days

    This still costs two days per release and grows with the product, so weekly releases stay hard and expensive.

The concept

Frequent small releases depend on technical practices such as test automation and continuous integration, which keep the product releasable without long manual checks.

Why that’s the answer

The bottleneck is a slow manual check. Automating it removes the delay while keeping full coverage on every change. Testing only the riskiest areas trades coverage for speed, releasing weekly to staging keeps users on a monthly cycle so feedback is no faster, and adding testers keeps a costly multi-day step that grows over time.

How to reason it out
  1. Find the bottleneck: four days of manual regression.
  2. Check the goal: weekly releases to users, at the same quality.
  3. Look for a change that removes the delay without reducing coverage.
  4. Reject options that test less or keep users on the old cycle.

Exam tip: Release frequency is limited by how fast you can prove nothing broke; automate that proof.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 21Delivery

A product owner wants the option to release a small increment to users whenever new work is ready, without waiting for a special release phase. Which TWO practices most directly make this possible? (Select TWO.)

Choose TWO.

  • a
    Pair programming on complex stories

    Pairing improves code quality and shares knowledge, but does not by itself make the product releasable on demand.

  • b
    Continuous integration of every change Correct

    Integrating and testing each change straight away keeps the product working, so it is always close to releasable.

  • c
    A definition of ready for backlog items

    A definition of ready helps items enter an iteration well understood. It does not affect whether the product can be released.

  • d
    A release plan agreed for each quarter

    A quarterly release plan schedules releases in advance; it does not make releasing possible whenever work is ready.

  • e
    An automated deployment pipeline Correct

    Automated, repeatable deployment means a release is a routine step rather than a special phase.

The concept

Continuous integration and automated deployment (together, continuous delivery) keep the product in a releasable state, so small increments can reach users as soon as they are done.

Why that’s the answer

Continuous integration keeps every change integrated and tested; an automated pipeline makes release a push-button step. Together they let the product owner release at any time. Pairing and a definition of ready improve work quality and flow into iterations, and a quarterly plan fixes timing rather than enabling it.

How to reason it out
  1. Ask what stops a team releasing at any moment: integration problems and manual deployment.
  2. Choose the practices that remove each of those.
  3. Reject practices that improve other things but not releasability.

Exam tip: Continuous integration plus automated deployment keep the product releasable at any moment.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 22Delivery

Usage data shows that 40% of new users abandon a new account-setup flow at step three, but it does not show why. The product owner wants to understand the reason before changing anything. Which technique should the team use next?

Choose one.

  • a
    Add a funnel chart of the flow’s steps to the team dashboard

    A funnel chart shows the same drop-off more visibly, but it still does not reveal why users leave.

  • b
    Send a satisfaction survey to registered users

    Most registered users finished setup, and a general satisfaction survey is unlikely to explain one step’s abandonment.

  • c
    Watch several new users try the flow in usability sessions Correct

    Observing people attempt step three shows where they hesitate and what confuses them, which is the missing "why".

  • d
    Run a split test of two alternative step-three designs

    A split test compares designs, but the team does not yet know what problem a new design should solve.

The concept

Each feedback technique suits a different question. Analytics show what happens and where; usability testing and interviews show why; split tests compare known alternatives.

Why that’s the answer

The team already knows where users drop out; it needs the reason. Watching users attempt the step reveals it directly. A funnel chart repeats the "where", a broad survey asks the wrong people the wrong question, and a split test is useful only once the team has an idea worth testing.

How to reason it out
  1. Identify what is known (where users leave) and what is missing (why).
  2. Match the missing piece to the technique that reveals reasons.
  3. Hold comparison tests until there is a hypothesis to test.

Exam tip: Analytics tell you where; watching users tells you why; split tests tell you which.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 23Delivery

A new invoicing feature is in pilot with 60 small businesses. The product owner has two open questions: how many pilot businesses actually use automatic payment reminders, and why some turned reminders off after a week. Which TWO techniques answer these questions most directly? (Select TWO.)

Choose TWO.

  • a
    A net promoter survey of the pilot businesses

    NPS measures overall loyalty. It answers neither how many use reminders nor why some stopped.

  • b
    Usage analytics on reminder settings across the pilot Correct

    Settings data shows exactly how many businesses have reminders on, answering the "how many" question without relying on memory.

  • c
    A demonstration of reminders at the next iteration review

    A demo collects reactions from review attendees, not evidence of how pilot businesses use the feature.

  • d
    A focus group with the internal finance department

    The finance department is not a pilot user of the invoicing feature, so it cannot explain the pilot businesses’ choices.

  • e
    Short interviews with businesses that turned reminders off Correct

    Talking to the businesses that switched off reveals their reasons, which data alone cannot show.

The concept

Quantitative feedback (analytics) answers "how many" and "how often"; qualitative feedback (interviews, observation) answers "why". Good feedback plans use each for the question it fits.

Why that’s the answer

The first question is a count, which usage data answers reliably. The second asks for reasons from a specific group, which short interviews with that group answer. NPS is too general, a review demo gathers opinions from attendees, and an internal focus group asks the wrong people.

How to reason it out
  1. Split the problem into its two questions.
  2. Match the "how many" question to behavioural data.
  3. Match the "why" question to conversations with the people who acted.
  4. Reject techniques aimed at the wrong group or a different question.

Exam tip: Use data for "how many" and conversations for "why", and ask the people who actually did it.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 24Delivery

Business stakeholders for a logistics platform review the product only at quarterly steering meetings. By then the team has usually built three months of work on assumptions, and some of it is rejected. The team works in two-week iterations. What should the agile practitioner do?

Choose one.

  • a
    Send the steering group a written progress report each month

    A report pushes information out but does not collect the stakeholders’ reactions to working product.

  • b
    Ask stakeholders to approve detailed requirements before each quarter

    Up-front approval of documents does not replace reacting to working product, so rejections would still come late.

  • c
    Invite the steering group to the team’s daily stand-up

    The daily stand-up is the team’s planning event for the day, not a forum for stakeholders to review the product.

  • d
    Review each increment with those stakeholders as it is done Correct

    Seeing each increment every two weeks lets stakeholders correct the direction before months of work pile up.

The concept

Stakeholder feedback should be collected on a regular, short cadence that matches delivery, so each increment can be adjusted before more work depends on it.

Why that’s the answer

Matching the feedback rhythm to the two-week delivery rhythm limits wasted work to one increment. A monthly report is one-way, quarterly approval of requirements still defers reaction to working product, and the stand-up is the wrong event for product feedback.

How to reason it out
  1. Compare the delivery cadence (two weeks) with the feedback cadence (quarterly).
  2. Look for an option that shortens the feedback cycle to match delivery.
  3. Prefer feedback on working product over documents or status reports.

Exam tip: Feedback should arrive as often as increments do; otherwise you build on guesses between reviews.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 25Delivery

The key users of a new medication-tracking tool are hospital pharmacists who can attend only one 30-minute session a month. The team works in two-week iterations, and the product owner wants pharmacist feedback on every increment. What should the agile practitioner suggest?

Choose one.

  • a
    Move the team to four-week iterations to match the session

    This halves the delivery and feedback rhythm for everyone, slowing learning to fit one meeting.

  • b
    Have the product owner relay pharmacists’ views from memory

    A proxy guessing what pharmacists would say is not their feedback, and errors in the guess go unnoticed.

  • c
    Let pharmacists try each increment in a sandbox and comment Correct

    Pharmacists can try each increment when it suits them and leave quick comments, and the monthly session goes deeper.

  • d
    Email pharmacists a recording of each iteration review

    A recording shows the increment but gives pharmacists no hands-on use and no simple way to respond.

The concept

When stakeholders have little time, feedback can be collected asynchronously, for example by giving them access to each increment and an easy way to comment, rather than slowing delivery to fit their calendar.

Why that’s the answer

Several options keep some feedback flowing, but only asynchronous hands-on access gives real pharmacist feedback on every increment without changing the team’s rhythm. Longer iterations slow everyone, a proxy substitutes guesses for feedback, and a video gives no hands-on experience or easy reply.

How to reason it out
  1. Note the constraint: little meeting time, but feedback wanted on every increment.
  2. Separate the feedback from the meeting.
  3. Prefer hands-on use by the real users over relayed views.
  4. Keep the team’s delivery rhythm unchanged.

Exam tip: If stakeholders cannot come to the increment, take the increment to them and make replying easy.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Keep going with PMI-ACP

PMI-ACP practice by domain

PMI-ACP sample questions: your questions

No. Real exam questions are confidential. These are original questions written to the skills in the official PMI-ACP exam guide, so they test the same knowledge in the same style without being copies of the exam.

Source

The domains and weights on this page come from the official PMI-ACP exam guide.