Before a fixed-date release, stakeholders and the product owner sort every candidate feature into four groups: required for the release to be viable, important but not vital, desirable if time allows, and agreed not to be delivered this time. Which prioritization technique are they using?
Choose one.
MoSCoW sorts scope into Must have, Should have, Could have and Won't have this time, which is useful when the date is fixed and scope flexes.
The four groups map one-to-one to MoSCoW. 'Agreed not to be delivered this time' is the Won't-have group that makes MoSCoW distinctive. The other techniques produce satisfaction categories, a ranked order or point weights.
- List the four groups in the stem.
- Map them to Must, Should, Could and Won't.
- Rule out techniques that produce scores or satisfaction categories.
Exam tip: Must, Should, Could, Won't (this time): MoSCoW is how fixed-date releases agree what can flex.
PMI-ACP Product Backlog Refinement: Clarifying, Prioritizing, Splitting and Sizing Backlog Items — the lesson that teaches this.