PMI-ACP Visualize Work: Kanban Boards, Burndown and Burnup Charts, and Cumulative Flow Diagrams

21 min readPMI-ACP · ProductUpdated

Visualizing work is the practice of showing all of a team's work, and the state of each item, on a board and a few charts that everyone can see, so the team and its stakeholders decide from current facts instead of status reports. It is a task in the Product domain of PMI's PMI-ACP Examination Content Outline, with three enablers: educate work visualization techniques, establish a process to update the data and statistics, and continuously share information. This lesson explains how to design a Kanban board or task board that mirrors the real workflow, how to make unplanned and cross-team work visible, how to read burndown charts, burnup charts and cumulative flow diagrams (including simple forecasts and Little's Law), how to agree working rules that keep the board's statistics trustworthy, and how to share one live source of data with every audience from the daily meeting to the portfolio.

What you’ll learn
  • Design a board whose columns mirror the team's actual workflow, including waiting states and Done sub-columns that let the next step pull work.
  • Distinguish an iteration task board from a continuous-flow Kanban board and choose the one that fits how a team works.
  • Make all of a team's work visible, including support work, classes of service, due dates, improvement actions and shared specialists' queues.
  • Coach a team and its stakeholders to introduce charts by need and read them correctly.
  • Interpret burndown, burnup and cumulative flow diagram patterns, and make one-step forecasts from them.
  • Establish working agreements for updating the board and recording dates so cycle time, throughput and blocked time can be trusted.
  • Share information continuously by giving each audience its own view of the same live data, including program and portfolio boards.

What visualizing work means

Visualizing work means showing every piece of a team's work, and the state each piece is in, in one place everyone can see, so the team and its stakeholders can spot problems and decide from facts instead of from memory or status reports. The usual tools are a board (a Kanban board or an iteration task board) and a small set of charts drawn from the same data: burndown charts, burnup charts and cumulative flow diagrams.

The PMI-ACP Examination Content Outline lists Visualize work as a task in the Product domain, with three enablers that give this lesson its structure:

  1. Educate work visualization techniques. Help the team, and the people around it, design boards that show the real work and read charts correctly.
  2. Establish a process to update the data/stats. Agree who updates the board, when a card moves and what gets recorded, so the statistics reflect reality.
  3. Continuously share information. Keep the picture current and let each audience see the view it needs, drawn from the same live data.

The three depend on each other. A board nobody understands is decoration; a board that is understood but updated late misleads; and accurate data that only the team can see does not help the sponsor who is about to make a decision. A visualization earns its place when it answers a question someone actually has: what should we finish next, where is work piling up, how much is left before the release goal is met?

Two neighbouring tasks are taught in their own lessons. Information radiators as a transparency practice, impediment visibility and the misuse of velocity belong to Build transparency; choosing and analysing delivery metrics, and using WIP limits to optimize flow, belong to the Delivery domain. Here, WIP limits appear only as something a board shows.

Designing a board that mirrors the real workflow

A board's columns should show the steps a team's work actually goes through today, including the steps where work waits, so that the position of a card tells the truth about that work. Columns represent workflow states. They do not represent people, priority levels or iterations; those are shown, if needed, by swimlanes, card order, colour or labels.

Map the process you run, not the one on paper

A good way to find the real steps is to trace a handful of recently finished items and write down every place each one went and every place it sat. Where that trace differs from the documented process, the board follows the trace. A board drawn from a process document, or from the process the team would like to have, hides exactly the behaviour that needs improving. Once the real flow is visible, the team can change it deliberately and redraw the board to match.

Show waiting, not just working

A board with one broad active column (To Do, Doing, Done) is a common start, but it stops being informative once most cards collect in the middle: the column cannot say whether an item is being worked on or is sitting in a queue. Picture a content team whose In progress column hides drafting, waiting for legal approval and waiting for translation. Splitting the active column into each real step, including the waiting steps, shows where items actually sit. Waiting is usually where most elapsed time goes, and a separate queue column is also what allows a tool's timestamps to measure it later.

Done sub-columns make pull possible

In a push system, each step hands work on as soon as it finishes, whether or not the next step has room. Splitting a step into In Progress and Done sub-columns turns that hand-off into a visible queue of finished work. The downstream step pulls from the queue when it has capacity, so its WIP limit can hold, and the upstream step can see the queue growing and slow down. The overload becomes visible instead of being absorbed by the next step.

The team designs its own board

The people who do the work know its steps, so they design the board, with the practitioner facilitating: asking questions, offering techniques and letting the team decide. A board imposed from outside, however well designed, describes someone else's work, and people have little reason to keep it current. A board the team designed is one the team owns and keeps changing as its process changes.

When leaders need a consistent roll-up across teams, consistency comes from agreeing a few shared states (for example, Not started, In progress, Done) and having each team map its own columns onto them. Each team keeps its own board; the higher-level view aggregates the mapped states.

Iteration task board or Kanban board

An iteration task board shows only the work the team planned for the current iteration and is cleared and set up again at each iteration's planning; a Kanban board shows continuous flow, with cards that keep moving across iterations and explicit WIP limits on its columns. Both are boards of the team's work; they typically differ in time horizon and in what limits the work.

Iteration task boardKanban board
ContentsStories (and often their tasks) committed for this iterationAll work in the flow, from intake to done
Lifespan of the layoutReset at each iteration's planningNever reset; cards flow continuously
What typically limits workThe iteration's capacity, set at planning (some teams add WIP limits too)Explicit WIP limits per column
Typical companion chartIteration burndownCumulative flow diagram, cycle time
Fits bestTimeboxed teams, such as ScrumContinuous arrival and release, such as support or operations

The choice follows how work arrives and leaves. Where work arrives continuously and each item is released when it is ready, there is no iteration plan for a task board or an iteration burndown to describe; a continuous-flow board fits. Neither board shows the whole product backlog ordered by value; that is the backlog itself, covered in the Refine product backlog lesson.

A team that moves from timeboxes to continuous flow also has to give up the periodic reset. Cycle time measures each item's unbroken journey from the moment work starts to the moment it is done, so the board has to keep that journey intact: one continuous board on which unfinished cards stay where they are when an iteration boundary passes.

Making all of the work visible

Everything the team spends capacity on belongs on its board, because work that is not visible competes for time unseen and makes the board unable to explain what the team delivers. The most common gap is unplanned work: production support, ad hoc requests from other departments, and improvement actions.

  • Unplanned and support work. When a large and varying share of capacity goes to work the board does not show, delivery looks erratic and nobody can see why. Giving that work its own card type (or swimlane) shows how much capacity it takes, so the team and product owner can plan with real data. The principle is to make the cause visible on the board itself, not to compensate for it elsewhere.
  • Classes of service. Not all work is treated the same. Expedite items, fixed-date items and standard work each need a distinct visual signal, such as a card colour or swimlane per class of service, and every fixed-date card shows its due date so the deadline is seen in time.
  • Improvement actions. Improvement work needs capacity just like feature work. Putting each agreed improvement on the board as a card makes it compete openly for that capacity and come up in the same daily conversation as everything else.
  • Shared specialists. A person or small group who serves several teams (say, a database administrator supporting four teams) needs one visible queue of everything requested. The requesting teams can see where their item stands, and the specialist has evidence for a conversation about priorities or capacity.

The test is simple: if the team does it, it is on the board. Making work visible is not the same as escalating it or giving it to one dedicated person; it is the step that lets everyone see the real load before deciding anything.

Teaching the team and stakeholders to use visualizations

Educating work visualization techniques means helping people build and read the visuals they need, one at a time, so that each one informs a decision. It is coaching, not a training course on a tool's features.

Introduce charts when a question needs them

Charts introduced before anyone has a question for them tend to be ignored, and a large set introduced together buries the useful ones. Start with the board, and add a chart when the team or a stakeholder asks something that the chart answers. The chart then has a purpose and an owner, and the team learns to read it while it matters.

Match the chart to the question

The question people are askingThe visual that answers it
Is this iteration on track to finish its plan?Iteration burndown
When will a defined body of release scope be complete, and how is that scope changing?Release burnup (completed work against total scope)
Where is work piling up in our process?Cumulative flow diagram
How long do individual items take, and how predictable is that?Cycle-time scatter plot or control chart
What is everyone working on right now, and what is stuck?The board itself

Teach people to read the chart

A chart only helps the people who can read it. When someone misreads one, the practitioner walks them through it in context: what each axis measures, what the ideal or reference line means and what direction counts as progress. Doing this together, on the real chart, builds a shared picture; it is part of the practitioner's job, not a one-off handout.

Sometimes the better fix is a different chart: a burndown can make real progress look like no progress when scope is added, and a burnup shows the same facts without that trap (see the burnup section below).

Reading iteration and release burndown charts

A burndown chart plots the work remaining (in story points, stories or task hours) on the vertical axis against time on the horizontal axis, with an ideal line running from the starting total to zero at the end of the iteration or release. The actual line shows what really remains each day; its shape tells the team how the work is flowing.

PatternWhat it most likely means
Flat for most of the iteration, then a sharp drop at the endMany items were worked in parallel and finished only at the end: too much started, too little finished. Smaller stories and a focus on finishing help. Check also that the board is updated as work finishes, since late updates produce the same shape.
Rises during the iteration with no stories addedNewly discovered tasks or larger-than-expected work. The team inspects at its daily meeting whether the iteration goal is at risk and talks to the product owner.
Ends above zeroNot all planned work was finished; a topic for planning and the retrospective, not for extending the iteration.
Follows the ideal line almost perfectly while stories stay unfinishedThe data is probably not real remaining work (see below).

Remaining work is a fresh estimate

When a team burns down task hours, the remaining figure for each task is re-estimated by the person doing it: how much is left now? Computing remaining work from the original estimate minus hours already spent measures effort, not progress, so the line falls on schedule whatever happens to the work. A rise in an honestly re-estimated burndown is useful information, not an error to smooth away.

Release burndowns and scope change

A release burndown shows the work left in a release. In its simple single-line form, completed work and added scope are netted together: in an iteration where the product owner adds more scope than the team completes, the line goes up and a reader may conclude the team did nothing. (Mike Cohn's alternative release burndown draws scope changes below the baseline to separate them.) When scope moves, a burnup shows the two facts most plainly.

Reading burnup charts and forecasting from them

A burnup chart has two lines: completed work, which rises as the team finishes items, and total scope, which moves only when work is added to or removed from the release. The release is done when the lines meet, so the gap between them is the work still to do.

Each line answers its own question. The scope line changes only when the release's content changes; the completed line changes only when work is finished. So a step in the scope line says something about scope decisions, not about the team's pace, and the team's pace is read from the completed line alone. Convergence depends on both: if scope grows as fast as work is completed, the gap stays the same size and the finish line keeps moving away, however steadily the team delivers. This separation is the main advantage of a burnup over a burndown.

Forecasting a range

Forecast from a burnup as a range, using the slowest and fastest velocity the team has actually shown, not a single figure from the average or the best iteration. Suppose total scope is 260 points, 100 are complete and recent velocity has run from 20 to 32. That leaves 160 points: 160 ÷ 32 = 5 and 160 ÷ 20 = 8, so the forecast is "between 5 and 8 more iterations". A range communicates uncertainty honestly and narrows as more iterations are completed.

When scope keeps growing

If scope rises steadily, the gap closes only at the difference between velocity and scope growth. Suppose scope is 150 points and grows about 6 points an iteration, 70 points are complete and velocity is about 22. The gap of 80 closes at about 22 − 6 = 16 points an iteration, so the lines meet in about 5 iterations; dividing the gap by velocity alone would promise about 4. Showing the trend lines on the chart lets the product owner decide whether to cap scope, reorder or accept the later date.

Reading a cumulative flow diagram

A cumulative flow diagram (CFD) plots, over time, the cumulative number of items that have reached each state of the workflow, with one coloured band per state, stacked from Done at the bottom to the first state at the top. Because the counts are cumulative, the lines never fall; a falling top line would indicate removed items or a data problem, not completed work.

Read thisTo see
Vertical gap between two lines on a given dayHow many items are between those states: the work in progress there
Horizontal gap between two linesApproximately how long items take to pass from one state to the other
Slope of the Done lineThroughput: how fast items are being finished
A band growing widerWork arriving in that state faster than it leaves: a bottleneck forming there
A band growing narrowerLess work in that state; it may be starved by the step before it
Height of the Done lineTotal items finished since the chart began, not this week's count

To find a bottleneck, look for the band that keeps widening while the bands before it hold steady and the Done line loses slope: work is entering that state faster than it leaves, and everything downstream is starved. The diagram points at the state to investigate; the team then asks why.

Cycle time from a CFD

Little's Law links the three readings: on average, cycle time ≈ work in progress ÷ throughput, as long as the flow is reasonably stable. For example, if the vertical distance between the started and finished lines has stayed around 24 items and the finished line climbs about 3 items a working day, items take roughly 24 ÷ 3 = 8 working days from start to finish. The horizontal gap between the same two lines gives the same estimate visually. Cycle time is a duration, so it always needs both inputs.

Keeping the board and its statistics current

Establishing a process to update the data means agreeing who moves cards, when they move and what is recorded on each item, so that the board shows the current state of the work and the statistics derived from it (cycle time, throughput, blocked time) can be trusted. It is a working agreement the team makes and keeps, not a reporting chore assigned to one person.

The person doing the work moves the card, at that moment

Each team member moves the cards for their own work as the work changes state. Any arrangement in which someone else updates the board on people's behalf, or updates it later, makes the board trail the real work, and the team then coordinates from stale information. Everyone who does the work therefore needs direct access to the board; for a distributed team that usually means an online board every member can update.

Record what the statistics will need

Flow statistics need dates. Cycle time needs the date each item started and the date it finished; throughput needs the finish dates. Teams on a physical board write these on the cards as they move, and a tool records them as timestamps. Lead time is a different, longer measure, taken from when an item was requested or committed to until it is delivered, so decide which question you want answered before choosing which dates to capture. Estimates and logged hours describe effort, not elapsed flow time. Blockers need dates too: recording when each block started and when it was cleared shows how much delay comes from outside dependencies.

Agree when a card moves

Tool timestamps are only as good as the moves behind them. Agreements that keep the data honest:

  • Define entry to each column by one observable event, written on the board as a policy, so everyone moves cards at the same point in the work.
  • Move cards as those events happen, one at a time, rather than catching up in batches.
  • Mark a blocked item as blocked where it is. Moving it backwards breaks its timing and makes the work in progress look smaller than it is.
  • To separate active time from waiting time, give each wait its own column, so entry and exit timestamps exist for both.

Statistics that look implausible are a signal to check the moving rules: if cards move long after the work did, the derived times are wrong. The fix is to correct the practice so that future data is right, keeping the record honest rather than editing or discarding inconvenient data.

Sharing information continuously, from the team to the portfolio

Continuously sharing information means keeping the visual picture of work available at all times and giving each audience the view it needs, derived from the same live data the team maintains, instead of producing separate reports that drift from reality.

Walk the board at the daily meeting

A daily meeting that goes round the people centres on individual activity, and items close to done can wait while new work starts. Walking the board from right to left, starting with the column nearest Done, centres the meeting on finishing. The conversation at each card is about the item, not its owner's activity: what is stopping it progressing, and who can help today.

Different audiences, one source of data

Different people need different levels of detail, but every view should be generated from the team's live board rather than rebuilt by hand:

  • Leaders and sponsors usually need an aggregated view, such as features or epics by state across teams, rolled up from the team boards.
  • Governance bodies with their own formats can have their reports populated from board data, with a link back to the live board.
  • External audiences can have a filtered, read-only view at the level they care about, which excludes internal or sensitive detail without creating a second board that someone must keep in step.

Hand-assembled reports and parallel trackers drift from the board, and then people argue about which figures are true.

Visualizing above one team

When several teams build one product, their dependencies need to be visible to all of them. A program board shows the features each team plans for the coming iterations, with the dependencies between them drawn as links, so anyone can see them at any time. At portfolio level, the typical problem is too many initiatives in progress at once, spread thinly across teams, so that little finishes. That is invisible on team boards, and it is fixed where initiatives are started: a portfolio board of initiatives with a limit on how many are active at once. Coordination structures such as scrum of scrums are covered in the lesson on a collaborative team environment.

Tip. Questions on this task are mostly short agile-team scenarios asking what the agile practitioner, scrum master or team should do, change, suggest or propose: a board whose columns hide where work waits or copy a documented process, a template imposed on a team, work that is missing from the board, charts that nobody uses or that stakeholders misread, cards moved late or by someone else, cycle-time data that looks wrong, status reports that disagree with the board, and visibility across several teams or a portfolio. Some items ask you to recognise a chart from its description, to choose the chart or board that answers a stated question, to interpret a burndown, burnup or cumulative flow diagram, or to make a one-step forecast from one, such as a range from a velocity range or cycle time from WIP and throughput. Some items are multiple response.

Key takeaways
  • Board columns are the team's real workflow steps, waiting steps included; not people, priorities or iterations.
  • A Done sub-column turns a push handoff into a visible queue the next step pulls from.
  • The team designs its own board; consistency across teams comes from mapping columns to a few shared states, not one template.
  • A task board holds one iteration's plan and is reset each iteration; a Kanban board never resets, and that unbroken flow is what cycle time measures.
  • If the team spends capacity on it, it goes on the board: support work, deadlines, classes of service and improvement actions.
  • Add a chart when a question needs it, choose the chart that answers that question, and teach people to read it.
  • A burndown that rises with no new scope means work was discovered; remaining hours are re-estimated, never estimate minus time spent.
  • Forecast from a burnup as a range from the slowest and fastest velocity; when scope grows, the gap closes at velocity minus growth.
  • On a CFD, vertical gap is WIP, horizontal gap is time, slope is throughput; a widening band is a bottleneck, and cycle time is about WIP divided by throughput.
  • Whoever does the work moves the card when the work moves, under agreed rules, and every audience's view is drawn from that same live data.

Frequently asked questions

What is the difference between a Kanban board and a task board?

An iteration task board holds only the work a team planned for its current iteration and is cleared and set up again at each iteration's planning. A Kanban board shows continuous flow: cards keep moving across the board without a periodic reset, and explicit WIP limits on its columns limit the work in progress. Timeboxed teams usually use a task board; teams whose work arrives and is released continuously usually use a Kanban board.

What should the columns of a Kanban board represent?

The columns of a Kanban board should represent the steps the team's work actually goes through today, including the steps where work waits, such as waiting for an approval or for another team. They should not represent team members, priority levels or iterations, and they should reflect the process the team really follows rather than a documented or ideal one.

How do you read a burndown chart?

A burndown chart shows the work remaining on the vertical axis against time, with an ideal line from the starting total down to zero. A line that stays flat and then drops at the end means work was finished late in a batch; a line that rises with no new scope means new work was discovered; a line that ends above zero means planned work was left unfinished.

What is the difference between a burndown chart and a burnup chart?

A burndown chart shows a single line of work remaining, so completed work and added scope are netted together and scope growth can hide progress. A burnup chart shows completed work and total scope as two separate lines; the release is finished when they meet, and changes in scope and in progress can each be seen on their own line.

How do you read a cumulative flow diagram?

A cumulative flow diagram stacks one band per workflow state, showing the cumulative count of items that reached each state over time. The vertical gap between lines is the work in progress, the horizontal gap is roughly how long items take between those states, and the slope of the Done line is throughput. A band that keeps widening shows work piling up in that state, which is a bottleneck.

How do you estimate cycle time from a cumulative flow diagram?

Use Little's Law: average cycle time is approximately average work in progress divided by average throughput, for a reasonably stable flow. For example, if about 24 items sit between the started and finished lines and the finished line rises by about 3 items a day, items take roughly 8 days from start to finish. The horizontal gap between the two lines gives the same approximation visually.

Who should update the agile board?

Each team member should move the cards for their own work at the moment the work changes state. When someone else updates the board on members' behalf, or updates happen in a batch later, the board trails the real work and statistics such as cycle time and throughput become unreliable.

How do you share an agile team's progress with executives or a PMO?

Give each audience a view derived from the team's live board rather than a separately written report. Leaders can follow an aggregated feature-level view rolled up from team boards; a governance body that needs its own format can have it populated from board data with a link to the live board; external audiences can get a filtered read-only view. One source of data keeps every audience's picture consistent.

Source

This lesson covers the "Product" domain of the official PMI-ACP exam guide. Vendors revise their guides — check the source for the current version.

Test yourself on this topic