PMI-ACP · Domain 4

Delivery practice questions

Delivery is worth 28% of the PMI-ACP exam — the heaviest of the 4 domains. Delivering with agile approaches: early feedback, agile metrics, impediments and risk, eliminating waste, continuous improvement, customer engagement and flow. Official weighting 28%. 6 fully worked examples are further down this page, answers included.

Exam weight
28%
the heaviest of the 4 domains
Questions
263
across 7 topics
Free, no account
5/day
a free account allows 10 a day
Explanations
Every option
right and wrong

Build a practice session

5 free questions left today.

Domains

How many?

Mode

Ready when you are

10 fresh questions drawn across 1 of 4 domains, in Learn mode.

Review what you missed

Every question you answer incorrectly, and every question you flag while practising, is saved here automatically. Finish a session and you can come back to re-drill just those.

6 sample Delivery questions, fully explained

Questions from the PMI-ACP bank mapped to domain 4, with the answer key and the reasoning behind every option. None of them repeat the examples on the main PMI-ACP practice page.

Question 1Delivery

The average satisfaction score for a hospital shift-scheduling app has stayed at 4.2 out of 5 over the last three increments. Broken down by role, nurse managers rose from 3.9 to 4.6, while night-shift nurses fell from 4.0 to 2.8. Night-shift nurses are about a third of users. What should the product owner do?

Choose one.

  • a
    Keep the current priorities, as the overall score is stable

    The stable average is the result of two opposite movements. Treating it as "no change" ignores a sharp fall for a large group.

  • b
    Prioritize what nurse managers request in the next increments

    Nurse managers are already the group whose satisfaction is rising. Serving them more does nothing for the group that is falling.

  • c
    Wait for more night-shift responses before drawing conclusions

    Nothing suggests the responses are unreliable. Waiting for more responses delays action on a clear three-increment trend.

  • d
    Find out how recent increments affected night-shift nurses Correct

    A large user group is getting steadily less satisfied. Finding out which changes caused that is the evidence-based next step.

The concept

An average satisfaction score can hide groups moving in opposite directions. Evaluating satisfaction includes segmenting by customer type and acting on a group whose experience is getting worse.

Why that’s the answer

The flat average masks a 1.2-point fall for a third of users. The product owner should find out what in recent increments hurt night-shift nurses. Keeping priorities trusts the misleading average, serving managers helps the group already improving, and chasing more responses delays action on a consistent trend.

How to reason it out
  1. Look past the average to the segments.
  2. Spot the group whose satisfaction is falling and how large it is.
  3. Link the fall to what changed in recent increments.
  4. Investigate that group before re-ordering the backlog.

Exam tip: A steady average can hide a group that is getting unhappier; segment before you conclude.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 2Delivery

A sponsor asks how the team will know whether customers are becoming more satisfied as a new customer portal grows. The team had planned one large satisfaction survey when the final release is complete. What approach fits agile delivery better?

Choose one.

  • a
    Measure satisfaction after each release and track the trend Correct

    Short, regular measurement shows whether each increment helped or hurt, while there is still time to respond.

  • b
    Run the full survey once the final release is complete, as planned

    One survey at the end gives no chance to change direction while the product is still being built.

  • c
    Ask the product owner to rate satisfaction each iteration

    The product owner’s view is a proxy. Customer satisfaction should come from the customers themselves.

  • d
    Count the stories the customer accepts at each review

    Accepted stories measure output against criteria, not how satisfied customers are using the product.

The concept

Agile teams evaluate customer satisfaction regularly, after each increment reaches customers, so the trend can guide the next increment.

Why that’s the answer

A trend measured release by release shows the effect of each increment and leaves time to adjust. An end-of-project survey comes too late to act on, a product owner’s rating is not the customer’s voice, and accepted stories measure output rather than satisfaction.

How to reason it out
  1. Ask when the information is needed: while there is time to change course.
  2. Prefer a short measure repeated after each release.
  3. Make sure the measure comes from customers, not proxies.

Exam tip: Measure customer satisfaction little and often, so each increment can be judged while you can still act.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 3Delivery

A company is rebuilding its internal expense-claim tool. The stated goal is to make submitting a claim less tedious for employees, who must use the tool because there is no alternative. The team will track one satisfaction measure after every increment. Which measure fits best?

Choose one.

  • a
    Number of employees actively using the tool each month

    Employees have no alternative, so they will use the tool however tedious it is. Active users would not move.

  • b
    Customer effort score from a short survey in the tool Correct

    The goal is about effort. A short in-tool question on how easy the claim was to submit, asked straight after doing it, measures the goal directly and after each increment.

  • c
    Net promoter score from a quarterly employee survey

    Recommending a mandatory internal tool means little to employees, and a quarterly survey is too slow to judge each increment.

  • d
    Number of expense claims submitted after each release

    Claim volume depends on business travel and spending, not on how tedious the tool is to use.

The concept

A satisfaction measure must fit both the goal and the audience. For a mandatory tool, usage measures reflect obligation rather than satisfaction, and a goal about ease calls for an effort measure.

Why that’s the answer

Two facts decide this: the users are captive, so usage-based measures stay flat whatever the experience, and the goal is about tedium, which is what customer effort score measures. Asking right after the task also gives a reading per increment. NPS fits loyalty in markets with choice and is collected too rarely here; claim volume is driven by business activity.

How to reason it out
  1. Note that users cannot switch, so usage does not reflect satisfaction.
  2. Note that the goal is about effort, not loyalty.
  3. Pick the measure that asks about effort at the moment of the task.
  4. Check that it can be read after every increment.

Exam tip: For captive users, usage is not satisfaction; measure what the goal names, at the moment of use.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 4Delivery

A sponsor asks why the team insists on putting a usable piece of the system in front of stakeholders every two weeks instead of delivering the whole system at the end. From a feedback point of view, what is the main benefit?

Choose one.

  • a
    Misunderstandings come to light while they are cheap to fix Correct

    Stakeholders react to real working pieces early, so wrong assumptions are found before much more work is built on them.

  • b
    Each small piece needs less testing than the full system would

    Small increments still need full testing to the definition of done; the benefit is not reduced testing.

  • c
    The total scope can be fixed earlier in the project

    Agile delivery keeps scope flexible so feedback can change it. Fixing scope early is the opposite of the aim.

  • d
    Stakeholders need to attend fewer meetings overall

    Frequent increments usually mean more regular stakeholder sessions, not fewer.

The concept

Delivering work in small increments shortens the time between building something and learning whether it is right, which lowers the cost of being wrong.

Why that’s the answer

Each small increment invites real feedback early, so mistaken assumptions are corrected before more work depends on them. Testing effort is not reduced, scope is deliberately kept open, and stakeholder involvement usually rises rather than falls.

How to reason it out
  1. Ask what small increments change about feedback timing.
  2. Link earlier feedback to the cost of correcting mistakes.
  3. Reject benefits that agile does not claim, such as less testing or fixed scope.

Exam tip: Small increments make mistakes cheap: you learn you are wrong before you have built much on top of it.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 5Delivery

A team is moving 40 types of customer records from a legacy system to a new platform and plans one cutover in month six. Business users say the only reliable way to check migrated data is to work with it in the new platform. What should the agile practitioner suggest?

Choose one.

  • a
    Migrate a few record types at a time and have users check each Correct

    Users work with each small batch soon after it moves, so mapping problems are found early and fixed before the next batch.

  • b
    Run one complete trial migration in month five for user checks

    A rehearsal helps, but users would see the data for the first time a month before cutover, leaving little time to fix what they find.

  • c
    Add automated reconciliation of record types to the single cutover

    Reconciliation confirms counts and totals match. It cannot tell whether the data is usable, which the users say only working with it shows.

  • d
    Have users sign off detailed mapping specifications first

    Signing documents is not working with the data. Users said that is the only reliable check, so errors would still surface late.

The concept

Large batches delay feedback until the end. Splitting work into small, usable increments lets the people who can judge quality check each piece early.

Why that’s the answer

The constraint is that only hands-on use reveals bad data. Migrating in small batches gives users that hands-on check within weeks, not months. A late trial migration and automated reconciliation are both useful, but the first gives feedback too late and the second cannot judge usability. Signed specifications are reviewed on paper, which the users have said is not reliable.

How to reason it out
  1. Identify who can judge the result and how: users, by working with the data.
  2. Ask when each option first gives them something to work with.
  3. Check whether automated or paper checks meet the stated constraint.
  4. Choose the option with the earliest real feedback per batch.

Exam tip: When only real use can judge quality, split the work so real use starts with the first small batch.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

Question 6Delivery

A team has finished a redesigned checkout for an online store. The product owner wants feedback from real customers before every customer sees it, because a flaw in checkout could hurt sales. What should the team do?

Choose one.

  • a
    Show it to the sales team and gather their views at the review

    Sales staff are not the customers who check out, and a demo gives no evidence of real buying behaviour.

  • b
    Release it to the whole customer base with rollback ready

    A rollback helps recovery, but every customer meets the flaw first, which is the risk the product owner wants to avoid.

  • c
    Hold it until staff complete a round of usability testing

    Staff testing is useful, but it is not feedback from real customers and it delays learning how buyers respond.

  • d
    Release it to a small share of customers and compare results Correct

    Real customers use it while most continue with the current checkout, so any flaw affects few sales and the comparison shows its effect.

The concept

Releasing an increment to a limited group of real users (a pilot, beta or canary release) gets genuine feedback early while limiting the impact if something is wrong.

Why that’s the answer

Both requirements are met only by a limited release: feedback comes from real customers, and exposure is small. A full release with rollback exposes everyone, while a sales demo and staff testing produce opinions from people who are not the customers.

How to reason it out
  1. List the two requirements: real-customer feedback and limited risk.
  2. Check each option against both.
  3. Pick the one that gives real use to a small group.

Exam tip: To learn from real users without betting everything, release to a few first and compare.

PMI-ACP Seek Early Feedback: Customer Satisfaction, Small Increments and Feature Flags — the lesson that teaches this.

What PMI-ACP domain 4 tests, topic by topic

The official exam guide breaks Delivery into 7 topics. The question bank follows the same split, so a weak topic shows up as a cluster of misses you can go back and read.

Published PMI-ACP practice questions per topic in Delivery
TopicWhat it coversQuestions
Seek early feedbackOfficial PMI-ACP ECO (November 2024, rev. March 2026), Domain IV Task 1. Enablers: Evaluate customer satisfaction; Deliver work in small increments; Collect and incorporate stakeholders' feedback on a regular basis.38
Manage agile metricsOfficial PMI-ACP ECO (November 2024, rev. March 2026), Domain IV Task 2. Enablers: Determine which metrics are appropriate for a given audience; Radiate metrics across the relevant audience; Review and analyze metrics; Use metrics insights for decision making.36
Manage impediments and riskOfficial PMI-ACP ECO (November 2024, rev. March 2026), Domain IV Task 3. Enablers: Proactively identify risks and impediments; Engage the team to find the most appropriate course of action; Prioritize impediment removal and risk mitigation activities; Monitor/control risks and impediments; Use lessons learned to avoid risks/impediments recurrence.38
Recognize and eliminate wasteOfficial PMI-ACP ECO (November 2024, rev. March 2026), Domain IV Task 4. Enablers: Visualize the end-to-end flow of value in the system (e.g., value added, non-value added); Use metrics, tools and feedback loops to identify waste; Prioritize waste reduction activities; Iterate on identification and reduction of waste.37
Perform continuous improvementsOfficial PMI-ACP ECO (November 2024, rev. March 2026), Domain IV Task 5. Enablers: Obtain metrics and feedback to drive continuous improvements; Implement improvement actions; Evaluate the effectiveness of process improvement.38
Actively engage customersOfficial PMI-ACP ECO (November 2024, rev. March 2026), Domain IV Task 6. Enablers: Identify and analyze customer and their needs; Validate that iteration deliverables meet acceptance criteria; Encourage collaboration between customer and team.38
Optimize flowOfficial PMI-ACP ECO (November 2024, rev. March 2026), Domain IV Task 7. Enablers: Limit work-in-progress at all levels; Shield team from interruptions (e.g., create team interfaces); Use metrics to analyze and improve flow.38
Total263

Revise Delivery before you drill it

Other PMI-ACP domains

Delivery: your questions

Delivery is domain 4 of the PMI-ACP exam guide and carries 28% of the scored content — the heaviest of the 4 domains. On a 120-question paper that works out to roughly 34 questions, though PMI does not publish an exact per-domain count and individual exam forms vary.