PMP sample questions — 25 answered and explained

25 PMP sample questions written to the official Project Management Professional (PMP) exam guide, grouped by exam domain and weighted like the real exam. Each shows the correct answer, why every other option is wrong, and the lesson that teaches it. None of them repeat the examples on the other PMP practice pages.

On this page
25
answers included
Full bank
1043
on the practice page
Domains
3
weighted like the exam
Free, no account
5/day
a free account allows 30 a day

Domain 1: People

33% of the PMP exam, so 8 of the 25 questions on this page.

Question 1People

Six months into an agile product effort, a competitor launches a similar product and the sponsor signals the target market may shift. The team is midway through an iteration. What should the project manager do?

Choose one.

  • a
    Stop the iteration and re-plan the product backlog with the team

    Cancelling the iteration and re-planning before the vision is confirmed reacts to a signal, not a decision, and wastes work that may still be valid.

  • b
    Revisit the vision with the product owner and the sponsor Correct

    A market shift may change the outcome the product should deliver. Reviewing the vision with its owners keeps it current before the backlog is reshaped.

  • c
    Continue as planned until the current release is complete

    Ignoring a signalled market shift risks delivering a release toward an outdated vision. Keeping the vision current is part of the task.

  • d
    Ask the sponsor to approve a change to rebaseline the release schedule

    Rebaselining the schedule assumes the answer before the vision has been reviewed. The schedule follows from the vision, not the other way around.

The concept

The vision must be kept current: when the business environment changes, the project manager prompts its owners to review it before the plan changes.

Why that’s the answer

A competitor launch and a possible market shift are exactly the triggers for revisiting the vision. The product owner and sponsor confirm whether it changes; only then does the backlog follow. Stopping the iteration is the tempting decisive move, but it acts before anyone knows whether the vision changes.

How to reason it out
  1. Recognize an external change that may affect the outcome sought.
  2. Recall that keeping the vision current is the project manager's job.
  3. Involve the people who own the product vision and business case.
  4. Defer re-planning until the vision is confirmed.

Exam tip: External change triggers a vision review first; plans follow the reviewed vision.

PMP Develop a Common Vision: Shared Vision, Ownership and Root Cause — the lesson that teaches this.

Question 2People

A predictive infrastructure project is approaching its phase gate. Since initiation, a new regulation has changed how the organization intends to use the finished asset. What should the project manager do to keep the project aligned?

Choose one.

  • a
    Review the objectives and vision at the phase gate with the sponsor Correct

    A phase gate is the governed point to confirm the project still serves its intended outcome. Bringing the changed intended use there keeps the vision current with the sponsor's agreement.

  • b
    Rewrite the vision statement before the phase gate and brief the team

    Rewriting the vision alone changes the project's direction without the sponsor's agreement. Briefing the team afterwards does not make it a shared vision.

  • c
    Leave the vision unchanged until the project reaches closure

    Waiting until closure means delivering an asset aligned to a purpose that no longer applies. Keeping the vision current is an ongoing task.

  • d
    Log the regulation as a risk and review it after the phase gate

    The regulation has already changed the intended use, so it is a present fact, not an uncertain risk. Logging it alone leaves the vision outdated.

The concept

Phase gates and other review points are natural moments to confirm the vision; changes in intended use are taken there with the sponsor.

Why that’s the answer

The intended use of the asset has changed, so the project's purpose may no longer match its objectives. The upcoming phase gate is the governed place to confirm that with the sponsor. Rewriting the vision alone is tempting because it updates the vision quickly, but it bypasses the sponsor.

How to reason it out
  1. Note that the intended use, and therefore the outcome, has changed.
  2. Note the timing: a phase gate is coming.
  3. Use the governed review point to confirm the vision with the sponsor.
  4. Reject unilateral rewrites, waiting and treating a fact as a risk.

Exam tip: Use governed review points such as phase gates to keep the vision current, with the sponsor.

PMP Develop a Common Vision: Shared Vision, Ownership and Root Cause — the lesson that teaches this.

Question 3People

On a hybrid project, the product owner and team agree the product vision should shift from cutting costs to retaining customers. That shift would change the objectives written in the signed charter. What should the project manager do next?

Choose one.

  • a
    Update the charter objectives to match the agreed product vision

    Editing a signed charter without the sponsor's approval bypasses governance. The team's agreement does not authorize a change to chartered objectives.

  • b
    Keep the original product vision because the charter is signed

    A signed charter does not freeze the vision forever. Ignoring a well-founded shift means delivering toward an outcome the product owner no longer believes in.

  • c
    Record the shift as an action from the next team retrospective

    A retrospective improves how the team works. It is not the forum that decides changes to chartered objectives.

  • d
    Take the proposed change to the sponsor for a decision Correct

    The charter's objectives were authorized by the sponsor. A vision change that alters them needs the sponsor's decision through governance before it becomes the project's direction.

The concept

Keeping the vision current includes routing vision changes that alter chartered objectives to the sponsor and governance for approval.

Why that’s the answer

The product owner and team agree on the shift, but it changes objectives the sponsor authorized. The right path is to bring the proposal to the sponsor. Updating the charter directly is tempting because everyone in the room agrees, but the authority to change chartered objectives sits with the sponsor.

How to reason it out
  1. Note that the vision change alters signed charter objectives.
  2. Recall who authorized those objectives: the sponsor.
  3. Follow the governed path rather than editing or ignoring.
  4. Choose the action that brings the proposal to the decision maker.

Exam tip: A vision change that alters chartered objectives goes to the sponsor; it is neither edited in nor ignored.

PMP Develop a Common Vision: Shared Vision, Ownership and Root Cause — the lesson that teaches this.

Question 4People

Three developers join an agile team mid-release. Within a week they question why certain backlog items are ranked highly and propose features unrelated to the release goal. Which TWO actions should the project manager take? (Select TWO.)

Choose TWO.

  • a
    Walk them through the product vision and the release goal Correct

    Newcomers did not take part in forming the vision, so explaining it, and how the release goal serves it, gives them the reason behind the ranking.

  • b
    Pair them with members who show how stories trace to the vision Correct

    Pairing lets experienced members show in daily work how stories connect to the vision, which promotes it far better than a one-off briefing alone.

  • c
    Ask the product owner to re-rank the backlog for the newcomers

    The ranking reflects the vision; changing it to suit people who do not yet understand the vision moves the product away from its outcome.

  • d
    Give them low-priority stories for the rest of the release

    Sidelining newcomers does not build their understanding of the vision and wastes their capacity on the least valuable work.

  • e
    Send them the product vision document and release plan to read

    Reading the vision gives awareness, not understanding. It does not show them why particular items rank highly or how their work connects to the release goal, which is what their questions reveal they are missing.

The concept

When people join mid-stream, the project manager re-establishes the vision with them so they understand why work is prioritized as it is.

Why that’s the answer

The questions and off-goal proposals show the newcomers lack the shared vision, not that the ranking is wrong. Explaining the vision and release goal, then reinforcing it through pairing, builds understanding two ways. Sending the documents is the tempting shortcut, but reading produces awareness, not the understanding that explains the ranking. Re-ranking the backlog bends the product to a misunderstanding.

How to reason it out
  1. Interpret the questions as a missing shared vision, not a ranking error.
  2. Choose actions that build the newcomers' understanding, not just their awareness.
  3. Prefer an explanation plus reinforcement in daily work over documents alone.
  4. Reject actions that change the product or sideline the people.

Exam tip: New people need the vision explained and reinforced; do not reshape the backlog around their gap.

PMP Develop a Common Vision: Shared Vision, Ownership and Root Cause — the lesson that teaches this.

Question 5People

On a Scrum-based agile team, which role is accountable for developing and communicating the product goal that expresses the product vision?

Choose one.

  • a
    Scrum master

    The scrum master serves the team and the product owner, for example by helping find techniques to define the product goal, but is not accountable for it.

  • b
    Developers

    Developers are accountable for building a usable increment each sprint. They contribute to refinement but do not own the product goal.

  • c
    Project management office

    A PMO sets standards and supports projects across the organization. It does not own an individual product's goal.

  • d
    Product owner Correct

    The Scrum Guide makes the product owner accountable for developing and explicitly communicating the product goal, which is the team's concrete expression of the product vision.

The concept

In Scrum, the product owner is accountable for the product goal and the product backlog; the scrum master and project manager help the team understand and use it.

Why that’s the answer

Accountability for the product goal sits with the product owner. The scrum master is the tempting choice because the role coaches the team and helps the product owner with techniques for goal definition, but helping is not owning.

How to reason it out
  1. Recall the three Scrum accountabilities.
  2. Match 'product goal and backlog' to the product owner.
  3. Separate helping with the goal (scrum master) from owning it.
  4. Rule out organization-level bodies.

Exam tip: The product owner owns the product goal; others help promote and apply it.

PMP Develop a Common Vision: Shared Vision, Ownership and Root Cause — the lesson that teaches this.

Question 6People

A project manager on a hybrid program notices that the team's iteration goals have drifted toward technically interesting work with little visible link to what the program is meant to achieve. The product owner restated the vision at the last review. What should the project manager do?

Choose one.

  • a
    Set the iteration goals for the team directly from the program plan

    Dictating goals takes ownership away from the team and treats the symptom. The team still would not connect its choices to the vision.

  • b
    Ask the team to explain how each iteration goal advances the vision Correct

    Asking the team to make the link explicit puts the vision into their own goal-setting, so the team corrects course itself and keeps ownership of its goals.

  • c
    Report the drift to the sponsor as a team performance issue

    Escalating before working with the team skips the obvious first step and frames a shared-understanding gap as a performance problem.

  • d
    Ask the product owner to restate the program vision more often

    The vision was restated recently and the drift continued, so the team already hears it. Repeating it more often is one-way; the gap is that the team does not use it when it sets goals.

The concept

Promoting the vision includes using it in planning: iteration goals should visibly trace to what the program is meant to achieve, and the team should make that link itself.

Why that’s the answer

The vision has been communicated, yet the goals still drift, so the gap is in how the team uses it, not in whether they have heard it. Asking the team to explain how each goal advances the vision makes the link part of their own planning. Having the product owner restate it more often is the tempting non-directive option, but it repeats the one-way message that already failed. Setting goals for the team is quick but removes ownership.

How to reason it out
  1. Note the vision was restated recently and the drift continued.
  2. Diagnose: the team hears the vision but does not use it when setting goals.
  3. Choose the action that puts the vision into the team's own planning.
  4. Reject repeating the message, command-and-control and early escalation.

Exam tip: If people have heard the vision but drift anyway, make them use it, not hear it again.

PMP Develop a Common Vision: Shared Vision, Ownership and Root Cause — the lesson that teaches this.

Question 7People

A project manager suspects that the agile team does not share a common understanding of the project vision. Which TWO observations would best support that suspicion? (Select TWO.)

Choose TWO.

  • a
    Velocity has dropped for two consecutive iterations

    A velocity drop has many causes (capacity, technical debt, story size). On its own it does not point to the vision, so it is weak evidence for this suspicion.

  • b
    Members disagree about which design pattern best suits a story

    Disagreeing on a design pattern is about how to build a story, not why it matters. Teams that share the vision still debate design.

  • c
    Members rank the same backlog items in very different orders Correct

    When people rank identical items very differently, they are using different ideas of what matters, which points to an unshared vision.

  • d
    Stakeholders request status updates more often than planned

    More status requests point to a communication or expectations issue with stakeholders, not to the team lacking a shared understanding of the vision.

  • e
    Members cannot explain how their current work serves the outcome Correct

    If people cannot link their work to the intended outcome, the vision is not guiding their work, which is the clearest sign it is not shared.

The concept

Symptoms of an unshared vision are about purpose and priority: divergent ranking of the same work and work no one can link to the outcome.

Why that’s the answer

Both correct observations show people using different reasons for their choices: they rank the same work differently and cannot link their work to the outcome. A velocity drop is tempting because vision confusion can slow a team, but it has many other causes and does not point anywhere specific. Design debates and extra status requests concern how work is built and reported, not why it is done.

How to reason it out
  1. Ask what a shared vision would change: priorities and purpose.
  2. Find observations about priority and purpose.
  3. Set aside observations that have many possible causes, such as velocity.
  4. Set aside observations about design or reporting.

Exam tip: Divergent priorities and work no one can link to the outcome signal an unshared vision.

PMP Develop a Common Vision: Shared Vision, Ownership and Root Cause — the lesson that teaches this.

Question 8People

On a hybrid project, a vendor's agile team built a reporting module around real-time dashboards, while the sponsor expected monthly regulatory reports. Both sides insist they followed the approved vision statement. The first regulatory report is due in eight weeks, and either version takes about five weeks to build. What should the project manager do first?

Choose one.

  • a
    Raise a change request for the vendor to rebuild the module

    A rebuild assumes the vendor misread the vision. The deadline leaves room for a short analysis first; rework started before the cause is known may be aimed at the wrong target, and the dispute will recur on the next module.

  • b
    Escalate to the sponsor to rule which reading is correct

    A ruling settles this module but not why the misunderstanding happened. Analysing the cause with both parties comes before escalation.

  • c
    Review the vision wording with both parties to locate the gap Correct

    Both sides acted in good faith on the same text, so the first job is to find where their readings diverge. That shows whether the cause is ambiguous wording, missing context or something else.

  • d
    Revise the approved vision statement to remove the ambiguous wording

    Revising the text may be the eventual fix, but it assumes the wording is the cause before anyone has checked, and it changes an approved artifact without analysis.

The concept

Breaking down a vision misunderstanding means finding where interpretations diverged before choosing a fix, so the corrective action addresses the actual cause.

Why that’s the answer

Two facts combine. Both parties followed the same approved statement and reached different results, so the divergence must be analysed before a fix is chosen. The deadline makes immediate action tempting, but eight weeks against a five-week build leaves time for a short, focused review. Raising a change request now is the strongest distractor under that pressure, yet it commits the vendor to a fix before anyone knows whether the wording, missing context or the sponsor's expectation is the cause. Revising the statement and escalating also act before understanding.

How to reason it out
  1. Note that both sides cite the same approved statement.
  2. Check the time pressure: eight weeks against a five-week build leaves room to analyse.
  3. Apply "analyse before acting" to find where the readings diverge.
  4. Choose the fix, change request or escalation only once the cause is confirmed.

Exam tip: Same text, different results: analyse the divergence before rewriting, reworking or escalating.

PMP Develop a Common Vision: Shared Vision, Ownership and Root Cause — the lesson that teaches this.

Domain 2: Process

41% of the PMP exam, so 10 of the 25 questions on this page.

Question 9Process

A project manager is determining critical information requirements for a hybrid project. The steering committee makes a monthly go/no-go decision, and a regulator requires quarterly energy-use figures. Which TWO should the project management plan define? (Select TWO.)

Choose TWO.

  • a
    Energy figures for the regulator in whatever format the tools export

    Starting from what tools export is backwards. The regulator's figures need a fixed definition and source, not whatever format happens to be convenient.

  • b
    Data the steering committee needs for each go/no-go decision Correct

    Critical information starts from the decisions it supports. Defining what the steering committee needs for go/no-go ensures the data is collected in time.

  • c
    Full sprint backlog detail for each steering committee decision

    Backlog detail is team-level working data. It adds volume without giving the committee the specific information its go/no-go decision depends on.

  • d
    Definition, source and owner of each energy figure for the regulator Correct

    A regulated figure needs a fixed definition, a data source and an accountable owner, or the quarterly report will be inconsistent or missing.

  • e
    Hour-level timesheets attached to each go/no-go decision pack

    Neither the committee's go/no-go decision nor the regulator's energy report needs hour-level timesheets; attaching them adds collection overhead without serving either consumer.

The concept

Critical information requirements are derived from the decisions and obligations the project must support, and specify what data, from where, owned by whom and when.

Why that’s the answer

The stem names two consumers: the steering committee's monthly decision and the regulator's quarterly figures. The plan must define the information each needs and make it reliable. Every option mentions one of the two consumers, but the distractors either start from convenient data (tool exports) or push detailed operational data upward (backlog detail, timesheets), which adds noise rather than serving the decision or the obligation.

How to reason it out
  1. List who needs information and why: the committee and the regulator.
  2. Derive the information from each need.
  3. Specify definition, source and owner for regulated metrics.
  4. Reject data chosen for convenience or volume.

Exam tip: Derive critical information from decisions and obligations, not from what is easy to collect.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Question 10Process

A manufacturer will replace its ERP system at 12 plants. Plants differ in their processes, unplanned downtime is very costly, the IT team can support one site's cutover at a time, and the budget excludes running two systems side by side. Which execution strategy should the project manager recommend?

Choose one.

  • a
    Cut over the 12 plants together on one weekend

    A big-bang cutover exceeds the IT team's one-site capacity and exposes every plant to downtime at once.

  • b
    Run old and new systems in parallel at each plant

    Parallel running is a sound way to cut downtime risk, but the budget explicitly excludes running two systems side by side.

  • c
    Roll out module by module across the 12 plants at once

    A module-by-module rollout still touches all 12 plants simultaneously, which the IT team cannot support and which spreads downtime risk widely.

  • d
    Pilot at one plant, then roll out plant by plant Correct

    A pilot proves the solution where processes differ, and a sequential rollout matches the one-site-at-a-time support limit while limiting the downtime exposure to one plant.

The concept

An execution strategy decides how the work is delivered: pilot, phased or big-bang rollout, parallel running, sequencing. The stated constraints decide among workable options.

Why that’s the answer

Several strategies could work in principle. The constraints eliminate them one by one: one cutover at a time rules out big-bang and all-plant module rollouts; no budget for two systems rules out parallel running. Differing plant processes and costly downtime favour proving the solution in one pilot plant before rolling out sequentially.

How to reason it out
  1. List the constraints: differing plants, costly downtime, one cutover at a time, no parallel budget.
  2. Test each strategy against every constraint.
  3. Eliminate big-bang and all-plant module rollout on capacity.
  4. Eliminate parallel running on budget; choose pilot plus phased rollout.

Exam tip: Pick the execution strategy that survives every stated constraint; pilot plus phased rollout limits risk when capacity is limited.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Question 11Process

A hybrid project must deliver a regulatory reporting module by a fixed legal deadline that leaves little slack, plus user-requested enhancements whose priority keeps shifting. The two specialists who know the reporting rules are also needed for most enhancements. Which execution strategy best fits?

Choose one.

  • a
    Finish the reporting module first, then iterate on enhancements Correct

    Focusing the scarce specialists on the deadline-bound module protects the legal date, and the shifting enhancements suit iterative delivery once it is done.

  • b
    Alternate whole sprints between the module and the enhancements

    Alternating halves the specialists' time on the module, which a deadline with little slack cannot absorb.

  • c
    Form two teams that deliver the two streams in parallel

    Parallel teams would normally speed delivery, but the same two specialists are needed by both streams, so splitting them slows the module.

  • d
    Deliver the enhancements first while the rules are being clarified

    Nothing in the stem says the rules need clarifying, and putting enhancements first consumes the little slack the module has before its legal deadline.

The concept

The execution strategy sequences and organizes work to meet the binding constraints, here a fixed legal date and a shared specialist bottleneck.

Why that’s the answer

Two facts combine: the legal deadline has little slack, and the specialists are a bottleneck shared by both streams. Any strategy that divides their time (alternating sprints, parallel teams) or delays the module (enhancements first) risks the deadline. Sequencing the module first, then using an iterative cadence for the shifting enhancements, fits both streams.

How to reason it out
  1. Identify the binding constraint: fixed legal deadline with little slack.
  2. Identify the bottleneck: two specialists needed by both streams.
  3. Reject options that split specialist time or delay the module.
  4. Sequence the module first, then iterate on the enhancements.

Exam tip: When a scarce resource serves two streams, sequence work to protect the fixed-date deliverable first.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Question 12Process

A project manager is preparing the baselines that earned value analysis will measure performance against on a predictive project. Which baselines together make up the performance measurement baseline?

Choose one.

  • a
    Scope, schedule and cost baselines Correct

    The performance measurement baseline integrates the scope, schedule and cost baselines; earned value compares actual performance against it.

  • b
    Scope, schedule and quality baselines

    Quality is planned in the quality management plan; there is no quality baseline in the performance measurement baseline, and the cost baseline is missing.

  • c
    Cost, quality and risk baselines

    Quality and risk are managed through subsidiary plans, not baselines in the performance measurement baseline, and scope and schedule are both missing.

  • d
    Schedule, quality and resource baselines

    Quality and resources are planned in subsidiary management plans, not as parts of the performance measurement baseline; scope and cost are missing.

The concept

The performance measurement baseline (PMB) is the integrated scope, schedule and cost baseline used to measure and manage project performance.

Why that’s the answer

Earned value needs to know what work was planned (scope), when (schedule) and at what cost (cost). Those three baselines together form the PMB. Quality, risk and resources are managed through subsidiary plans, not as parts of the PMB.

How to reason it out
  1. Recall what earned value compares: planned work, timing and cost.
  2. Match each to its baseline: scope, schedule, cost.
  3. Reject sets that add plans which are not baselines.

Exam tip: Performance measurement baseline = scope + schedule + cost baselines.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Question 13Process

On a predictive infrastructure project, the project manager is sorting planning outputs into two groups: items that are revised only through change control, and project documents, which are updated as work proceeds. Which TWO belong in the first group? (Select TWO.)

Choose TWO.

  • a
    Project schedule

    The project schedule is a project document that is updated as work progresses. Its approved version, the schedule baseline, is the plan component.

  • b
    Cost estimates

    Cost estimates are a project document. They feed the cost baseline but are not themselves part of the plan.

  • c
    Scope baseline Correct

    Baselines are components of the project management plan; the scope baseline is the approved scope statement, WBS and WBS dictionary, and it changes only through change control.

  • d
    Change management plan Correct

    The change management plan is a component of the project management plan: it describes how change requests are handled, and it is itself changed only through change control.

  • e
    Change log

    The change log is a project document that records change requests and their status as they occur; it is updated continuously, not revised through change control.

The concept

The project management plan holds the subsidiary management plans (including the change management plan) and the baselines. Working outputs such as the current schedule, estimates, registers and logs are project documents.

Why that’s the answer

Baselines and subsidiary management plans are approved parts of the plan that change only through change control. The scope baseline and the change management plan both qualify. The project schedule and cost estimates are the tempting near-twins: they look like the schedule and cost baselines, but they are working documents updated as work proceeds. The change log is a project document that records changes; it is not itself a controlled plan component.

How to reason it out
  1. Ask of each item: is it an approved part of the plan, controlled through change control?
  2. Baselines and subsidiary management plans are plan components.
  3. Working versions (schedule, estimates) and logs are project documents.

Exam tip: Baselines and management plans are in the plan; the working schedule, estimates and logs are project documents.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Question 14Process

Two weeks into initiation, the sponsor asks for a rough cost figure for a new regional warehouse. Few details are known, but the organization completed a very similar warehouse last year. Which estimating technique should the project manager use?

Choose one.

  • a
    Analogous estimating Correct

    Analogous estimating scales the actual cost of a similar past project. It is quick and suits early phases when detail is limited.

  • b
    Bottom-up estimating

    Bottom-up estimating needs decomposed work packages, which do not exist this early.

  • c
    Parametric estimating

    Parametric estimating needs a statistical relationship such as cost per square metre and reliable quantities; the stem offers a whole similar project instead.

  • d
    Three-point estimating

    Three-point estimating needs optimistic, most likely and pessimistic values for defined work; it does not replace having a comparable project.

The concept

Analogous (top-down) estimating uses the actuals of a similar past project to estimate a new one when little detail is available.

Why that’s the answer

The stem gives two clues: little detail and a very similar past project. Together they describe analogous estimating, which is fast but less accurate. Bottom-up needs a WBS; parametric needs a unit-rate model; three-point needs ranges for defined activities.

How to reason it out
  1. Note the timing: early, few details.
  2. Note the available data: one similar past project.
  3. Match whole-project comparison to analogous estimating.

Exam tip: Early, little detail, similar past project: use analogous estimating.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Question 15Process

A newly formed agile team inherits a product backlog of about 300 user stories. The product owner needs a rough size for each story by the end of a single half-day session to build an initial release plan. Which technique should the team use?

Choose one.

  • a
    Planning poker

    Planning poker builds consensus story by story through discussion, which is too slow for about 300 stories in half a day.

  • b
    Affinity estimating Correct

    Affinity estimating has the team place many items into relative size groups quickly, which suits sizing a large backlog in one session.

  • c
    Bottom-up estimating

    Bottom-up estimating breaks work into tasks and sums them, which is far too detailed for rough sizing of a whole backlog.

  • d
    Parametric estimating

    Parametric estimating relies on a unit-rate model from historical data, which a newly formed team does not have for its stories.

The concept

Agile teams use relative sizing. Affinity estimating sizes large numbers of items quickly; planning poker is better for refining a smaller set with discussion.

Why that’s the answer

The constraint is volume against time: about 300 stories in one half-day. Affinity estimating groups items by relative size rapidly, giving the rough sizes a release plan needs. Planning poker is the near-twin, another relative technique, but it discusses each item and would not finish.

How to reason it out
  1. Note the volume: about 300 stories.
  2. Note the time box: one half-day, rough sizes only.
  3. Pick the relative technique built for speed at volume.
  4. Reject planning poker on speed and bottom-up on detail.

Exam tip: Large backlog, rough sizes fast: affinity estimating; smaller set with discussion: planning poker.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Question 16Process

On a predictive project, the estimates for one activity are 4 days optimistic, 7 days most likely and 16 days pessimistic. Using a beta (PERT) distribution, what is the expected duration?

Choose one.

  • a
    8 days Correct

    Beta (PERT): (4 + 4 x 7 + 16) / 6 = 48 / 6 = 8 days.

  • b
    9 days

    9 days is the triangular average (4 + 7 + 16) / 3, which does not weight the most likely value.

  • c
    7 days

    7 days is the most likely value alone; PERT combines it with the optimistic and pessimistic values.

  • d
    10 days

    10 days is the midpoint of optimistic and pessimistic, which ignores the most likely value entirely.

The concept

Three-point estimating with a beta (PERT) distribution weights the most likely value four times: E = (O + 4M + P) / 6.

Why that’s the answer

Apply the formula: (4 + 28 + 16) / 6 = 8 days. The triangular average (9 days) is the main trap; it gives each value equal weight.

How to reason it out
  1. Identify O = 4, M = 7, P = 16.
  2. Apply beta: (O + 4M + P) / 6.
  3. Compute 48 / 6 = 8 days.

Exam tip: PERT (beta) = (O + 4M + P) / 6; triangular = (O + M + P) / 3.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Question 17Process

A work package is estimated at 80 hours of effort. Two developers will share it, each assigned to it for 4 hours of their 8-hour working day. Assuming no other constraints, how long will the work package take?

Choose one.

  • a
    5 working days

    5 days assumes both developers work on it full-time (16 hours a day), ignoring their 50% allocation.

  • b
    20 working days

    20 days assumes one developer at 4 hours a day, ignoring the second developer.

  • c
    10 working days Correct

    Together the developers contribute 2 x 4 = 8 hours per day, so 80 hours of effort takes 10 working days.

  • d
    40 working days

    40 days divides the effort by 2 hours a day, which matches neither the number of people nor their allocation.

The concept

Effort is the labour needed (person-hours); duration is calendar time. Duration = effort / (people x hours each per day).

Why that’s the answer

The two developers supply 8 effort-hours per working day between them, so 80 hours takes 10 working days. The distractors come from ignoring either the allocation or one of the two people.

How to reason it out
  1. Separate effort (80 hours) from duration (days).
  2. Compute daily capacity: 2 people x 4 hours = 8 hours.
  3. Divide: 80 / 8 = 10 working days.

Exam tip: Duration = effort divided by the hours actually available per day.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Question 18Process

An agile team of six delivered 28, 30 and 32 story points in its last three ten-day iterations. In the next iteration two members will be on leave for the whole iteration, and a public holiday removes one day for everyone. The top of the backlog holds 34 points. About how many points should the team plan?

Choose one.

  • a
    About 20 points

    20 points adjusts for the two people on leave but ignores the public holiday that removes a day for the remaining four.

  • b
    About 27 points

    27 points adjusts for the holiday but ignores the two members who are away for the whole iteration.

  • c
    About 18 points Correct

    Average velocity is 30. Four of six people remain (2/3) for 9 of 10 days (0.9): 30 x 2/3 x 0.9 = 18 points.

  • d
    About 34 points

    34 points is the size of the backlog slice, not the team's capacity; it exceeds even the team's normal velocity.

The concept

Velocity is a measure of a team's capacity under normal conditions. When capacity changes (absences, holidays), the plan is scaled to the capacity actually available.

Why that’s the answer

Two capacity reductions combine. Two of six people are away (keeping 2/3 of capacity) and one of ten days is a holiday (keeping 0.9). Applying both to the 30-point average gives about 18 points. Each near-twin applies only one of the adjustments; planning to the backlog slice ignores capacity entirely.

How to reason it out
  1. Take average velocity: (28 + 30 + 32) / 3 = 30.
  2. Scale for people: 4 of 6 = 2/3.
  3. Scale for days: 9 of 10 = 0.9.
  4. Multiply: 30 x 2/3 x 0.9 = 18 points.

Exam tip: Plan to available capacity: scale velocity for every reduction, not just the obvious one.

PMP Integrated Project Management Plan: Approach, Estimating and Plan Delivery — the lesson that teaches this.

Domain 3: Business Environment

26% of the PMP exam, so 7 of the 25 questions on this page.

Question 19Business Environment

A project manager joins a company whose PMO requires every project to use its templates and reporting formats, and audits projects for compliance with them. The PMO does not assign project managers or manage projects directly. Which type of PMO is this?

Choose one.

  • a
    A supportive PMO

    A supportive PMO offers templates, training and lessons learned on a consultative basis without requiring compliance.

  • b
    A directive PMO

    A directive PMO takes control of projects by directly managing them and assigning project managers, which this PMO does not do.

  • c
    A controlling PMO Correct

    A controlling PMO provides support and requires compliance with its frameworks, templates and governance, often checked through audits.

  • d
    A portfolio steering committee

    A steering committee is a decision-making body for priorities and funding, not an office that mandates templates and audits compliance.

The concept

PMOs differ by the degree of control they exert: supportive (low), controlling (moderate) and directive (high).

Why that’s the answer

Mandatory templates plus compliance audits, without managing projects directly, is the moderate level of control that defines a controlling PMO. The supportive PMO is the near-twin because it also provides templates, but it does not require their use.

How to reason it out
  1. Note what the PMO requires: use of its templates and compliance audits.
  2. Note what it does not do: assign or manage project managers.
  3. Match moderate control to the controlling PMO.
  4. Reserve directive for PMOs that run the projects.

Exam tip: Supportive suggests, controlling requires and audits, directive runs the projects.

PMP Project Governance: Decision Rights, Escalation Thresholds and Success Metrics — the lesson that teaches this.

Question 20Business Environment

A sponsor approves a new predictive project to reduce warehouse picking errors. The project manager is planning how the project will later be judged a success. When should the success metrics be defined?

Choose one.

  • a
    During initiation, agreed with key stakeholders Correct

    Success metrics are defined early and agreed with stakeholders so planning, reporting and acceptance all aim at the same measurable target.

  • b
    At closure, based on what was finally delivered

    Defining success after delivery lets the result define the target. It gives no guidance during the project and invites disputes.

  • c
    After the first status report reaches the sponsor

    Waiting until reporting has started means early decisions were made without an agreed measure of success.

  • d
    When the first deliverable has been accepted

    Acceptance of one deliverable is too late to steer the project toward agreed outcomes from the start.

The concept

Success metrics are part of governance: defined at the start, agreed with stakeholders and used throughout to steer and judge the project.

Why that’s the answer

Metrics set during initiation give the team a target for planning and give governance bodies a basis for oversight. Setting them later lets the outcome define the target and removes their value for steering.

How to reason it out
  1. Ask what success metrics are for: steering and judging the project.
  2. Steering requires them before work starts.
  3. Agreement with stakeholders prevents later disputes.
  4. So define them at initiation.

Exam tip: Agree how success will be measured before the work starts, not after it ends.

PMP Project Governance: Decision Rights, Escalation Thresholds and Success Metrics — the lesson that teaches this.

Question 21Business Environment

An agile team is building tools for a contact centre. The business case says the project exists to reduce average call handling time. The team proposes reporting features delivered per iteration as its success measure. Which measure should the project manager agree with stakeholders instead?

Choose one.

  • a
    Number of call handling features accepted per iteration

    Features accepted is an output measure, even when the features target call handling. The team could deliver many of them without shortening calls.

  • b
    Percentage of the planned release scope completed on time

    Scope completion measures delivery against plan, not whether calls became shorter.

  • c
    Call handling time compared with the baseline Correct

    Success is the outcome the business case promises. Measuring handling time against a baseline shows whether that outcome is achieved.

  • d
    Average team velocity across the last three iterations

    Velocity is a team planning tool. It says nothing about the business outcome and is not a success metric.

The concept

Project success metrics should measure the outcome or benefit in the business case, not only the outputs produced.

Why that’s the answer

The business case justifies the project by reduced handling time, so success is measured by handling time compared with a baseline. Features delivered and scope completed are tempting because they are easy to count, but they measure output and can look healthy while the outcome fails.

How to reason it out
  1. Read the business case: the purpose is shorter calls.
  2. Separate outcome measures from output and team measures.
  3. Choose the measure that tracks the outcome against a baseline.

Exam tip: Measure success by the outcome the business case promises, not by how much was produced.

PMP Project Governance: Decision Rights, Escalation Thresholds and Success Metrics — the lesson that teaches this.

Question 22Business Environment

A hybrid project is building a self-service renewals portal. The business case says success is a 20% rise in online renewals within six months of launch, delivered within the approved budget. Which TWO metrics should the project manager include in the success criteria reported to governance? (Select TWO.)

Choose TWO.

  • a
    Story points each project team completes per iteration

    Story points are a team estimation and planning measure. They are not comparable across teams and do not show business success.

  • b
    Online renewal rate compared with the pre-launch rate Correct

    This measures the outcome the business case names: the rise in online renewals.

  • c
    Cost performance against the approved project budget Correct

    The business case also makes delivery within budget a success condition, so cost performance belongs in the success criteria.

  • d
    Number of online renewal screens built and released

    Screens built is an output count. It can rise while online renewals stay flat.

  • e
    Count of budget change requests approved by the sponsor

    Counting budget change requests describes project activity, not whether the renewal outcome or the budget condition was met.

The concept

Success criteria trace back to the business case: the benefit it promises and the constraints it sets.

Why that’s the answer

The business case gives two conditions: a measurable rise in online renewals and delivery inside the approved budget. One metric tracks each. Story points and screens built are tempting because agile teams report them, but they measure effort and output rather than success.

How to reason it out
  1. Extract each success condition from the business case.
  2. Find a metric that measures each condition directly.
  3. Reject team planning measures and output counts.
  4. Keep one metric per condition.

Exam tip: Each success condition in the business case needs a metric that measures it directly.

PMP Project Governance: Decision Rights, Escalation Thresholds and Success Metrics — the lesson that teaches this.

Question 23Business Environment

An agile team will release an online claims form in three months. The agreed success metric is a 30% cut in claim processing time. The project manager finds that nobody has recorded how long claims take today. What should the project manager do?

Choose one.

  • a
    Use the industry average processing time as the baseline

    An industry figure is not this organization's starting point, so a measured change against it would not prove the project's effect.

  • b
    Measure processing time after release and compare it with the target

    Without a pre-release figure, a post-release measurement cannot show a 30% cut.

  • c
    Arrange to measure current processing time before the release Correct

    A reduction can only be shown against a baseline. Measuring now, before the release changes the process, is the only way to get a true baseline.

  • d
    Replace the metric with on-time delivery of the claims form

    Swapping an outcome metric for a delivery metric changes the agreed success criteria and stops measuring the benefit.

The concept

A success metric expressed as a change needs a baseline captured before the project alters the thing being measured.

Why that’s the answer

A 30% cut is a relative target, so the current value must be known. Once the new form is live, the old process can no longer be measured, which is why the baseline must be captured now. Using an industry average looks efficient but does not describe this organization.

How to reason it out
  1. Notice the metric is a relative change.
  2. A relative change needs a starting value.
  3. The starting value disappears once the release changes the process.
  4. Capture it now from the current process.

Exam tip: A metric of change is meaningless without a baseline measured before the change.

PMP Project Governance: Decision Rights, Escalation Thresholds and Success Metrics — the lesson that teaches this.

Question 24Business Environment

A predictive project's governance allows the project manager to resolve schedule variances of up to five working days; larger variances go to the sponsor. A supplier delay creates a forecast variance of three working days. What should the project manager do?

Choose one.

  • a
    Escalate the variance to the project sponsor

    Escalating a variance inside the agreed tolerance wastes the sponsor's time and ignores the delegated authority.

  • b
    Refer the variance to the steering committee

    The steering committee sits above the sponsor in the path. A within-tolerance variance does not reach it.

  • c
    Wait until the variance exceeds five days

    Being within tolerance means the project manager owns the response, not that the variance can be ignored.

  • d
    Respond to the variance and record it Correct

    The variance is inside the project manager's delegated tolerance, so the project manager handles it and records it for reporting.

The concept

Governance thresholds (tolerances) delegate decisions to the project manager inside a limit and require escalation above it.

Why that’s the answer

Three days is within the five-day tolerance, so the decision is the project manager's. Escalating is the tempting cautious choice but it defeats the purpose of a threshold, and doing nothing confuses having authority with having no duty to act.

How to reason it out
  1. Compare the variance with the threshold.
  2. Inside the threshold, the project manager acts.
  3. Record the variance so reporting stays transparent.
  4. Escalate only when the threshold is, or is forecast to be, breached.

Exam tip: Inside tolerance, act and record; outside tolerance, escalate.

PMP Project Governance: Decision Rights, Escalation Thresholds and Success Metrics — the lesson that teaches this.

Question 25Business Environment

On a predictive project, the governance sets a cost tolerance of 10% before the sponsor must decide. The current cost variance is 7%, and the estimate at completion shows it will reach 13% next quarter. The project manager has spent the contingency reserve. What should the project manager do?

Choose one.

  • a
    Wait until the actual variance passes 10% before escalating

    Waiting for the actual breach removes the sponsor's time to act. Thresholds exist to trigger decisions when a breach is forecast.

  • b
    Draw on the management reserve to cover the forecast overrun

    The management reserve is held outside the cost baseline and released only by management, normally the sponsor. The project manager cannot draw it unilaterally.

  • c
    Cut lower-priority scope to keep the forecast under 10%

    Cutting scope changes the agreed baseline and benefits. Doing it to avoid escalation bypasses governance.

  • d
    Escalate to the sponsor now with the forecast and options Correct

    A forecast breach is a reason to escalate early. The sponsor controls the management reserve and the decision, so the project manager brings the forecast and options now.

The concept

Escalation thresholds are applied to forecasts as well as actuals, and reserves outside the project manager's control require escalation.

Why that’s the answer

Two facts decide this. First, the estimate at completion forecasts a breach, so escalation is due now while the sponsor still has options. Second, with contingency spent, the remaining money is management reserve, which the project manager cannot release. Drawing on it is the tempting fix, and cutting scope looks proactive, but both act outside the project manager's authority.

How to reason it out
  1. Compare the forecast, not just the current variance, with the tolerance.
  2. A forecast breach triggers escalation.
  3. Check what the project manager controls: contingency is spent.
  4. Management reserve and scope reductions need the sponsor's decision.
  5. Escalate now with the forecast and options.

Exam tip: Escalate on a forecast breach, and remember the management reserve is not the project manager's to spend.

PMP Project Governance: Decision Rights, Escalation Thresholds and Success Metrics — the lesson that teaches this.

Keep going with PMP

PMP practice by domain

PMP sample questions: your questions

No. Real exam questions are confidential. These are original questions written to the skills in the official PMP exam guide, so they test the same knowledge in the same style without being copies of the exam.