Six months into an agile product effort, a competitor launches a similar product and the sponsor signals the target market may shift. The team is midway through an iteration. What should the project manager do?
Choose one.
The vision must be kept current: when the business environment changes, the project manager prompts its owners to review it before the plan changes.
A competitor launch and a possible market shift are exactly the triggers for revisiting the vision. The product owner and sponsor confirm whether it changes; only then does the backlog follow. Stopping the iteration is the tempting decisive move, but it acts before anyone knows whether the vision changes.
- Recognize an external change that may affect the outcome sought.
- Recall that keeping the vision current is the project manager's job.
- Involve the people who own the product vision and business case.
- Defer re-planning until the vision is confirmed.
Exam tip: External change triggers a vision review first; plans follow the reviewed vision.