A project manager is starting a project in an organization with a long-established PMO. Before the kickoff, the project manager must set up status reporting, approval rules and document control for the project. What should the project manager do first?
Choose one.
Organizational process assets (OPAs) are the plans, policies, procedures, templates and knowledge bases of the performing organization, and they are the basis for establishing project governance.
Governance is described and established through the organization's process assets. An established PMO almost certainly owns reporting templates, approval policies and document control procedures, so the project manager reviews and tailors those rather than inventing new ones or borrowing rules from elsewhere.
- Recognise that reporting, approval and document control rules are governance.
- Ask what the organization already provides for them.
- Start from the organization's process assets.
- Tailor them to the project once they are understood.
Exam tip: Establish governance from the organization's process assets, then tailor.