During a Sprint, who decides which Developer works on which item in the Sprint Backlog?
Choose one.
A self-managing team decides internally who does what; the Sprint Backlog belongs to the Developers.
The Scrum Guide says the team decides internally who does what, when and how, and calls the Sprint Backlog a plan by and for the Developers. Allocation by the Scrum Master, the Product Owner or a senior Developer would put a person above the team's collective decision, which conflicts with self-management and with the rule that a Scrum Team has no hierarchies.
- Identify the decision: who works on which Sprint Backlog item.
- Recall that this is one of the "who, when, how" decisions made inside the team.
- Reject options that give the decision to one person, whatever their accountability or seniority.
Exam tip: Nobody assigns Sprint work to the Developers; they decide it together.