Test levels and test types are the two ways the CTFL syllabus slices testing: a test level is a group of test activities organised and managed together for software at one stage of development (component, component integration, system, system integration, acceptance), while a test type is a group of activities aimed at a particular quality characteristic or test basis (functional, non-functional, black-box, white-box). This lesson covers CTFL v4.0.1 section 2.2: the attributes that tell the five levels apart, the forms of acceptance testing, the four test types and how they apply at every level, and the difference between confirmation testing and regression testing after a change.

What you’ll learn
  • Distinguish the five test levels by test object, objectives, test basis, typical defects, approach and responsibilities
  • Tell component integration testing from system integration testing, and system testing from acceptance testing
  • Recognise the forms of acceptance testing: user, operational, contractual, regulatory, alpha and beta
  • Distinguish functional from non-functional testing and black-box from white-box testing
  • Explain why every test type can be applied at every test level
  • Distinguish confirmation testing from regression testing and apply both, with impact analysis, after a change

What is a test level?

A test level is a group of test activities that are organised and managed together, and each level is an instance of the test process carried out on the software at a particular stage of development. The same activities (planning, analysis, design, implementation, execution, completion) happen at every level; what changes is what is being tested and why.

The CTFL syllabus names five test levels:

  1. Component testing (also called unit testing)
  2. Component integration testing (also called unit integration testing)
  3. System testing
  4. System integration testing
  5. Acceptance testing

To keep levels from overlapping in purpose, they are distinguished by a set of attributes (the list is not exhaustive):

  • Test object – what is tested (a component, a group of components, the whole system, its interfaces with other systems).
  • Test objectives – what the level is trying to achieve.
  • Test basis – the work products the tests are derived from.
  • Defects and failures – the kinds of problems the level typically finds.
  • Approach and responsibilities – how the level is carried out and who does it.

Notice what is not on that list: quality characteristics such as performance or usability. Those distinguish test types, which cut across every level (see below).

How levels relate to the lifecycle

In sequential development models, the exit criteria of one level often form part of the entry criteria for the next, so the levels run as a chain. In some iterative models this does not apply: development activities can span several test levels, and test levels can overlap in time. How the lifecycle as a whole shapes testing is covered in the lesson on testing in the context of an SDLC.

Component testing and component integration testing

Component testing checks components in isolation, and component integration testing checks the interfaces and interactions between those components. Both look inward at the parts of a single system.

Component testing

The test object is one component (a class, a module, a function) separated from the rest of the system. Isolation usually needs specific support: test harnesses and unit test frameworks, with dependencies such as a database or another service replaced by stubs or other test doubles. Component testing is normally performed by developers in their own development environments. Test doubles let a component be exercised without the components it depends on; checking how the real components then work together is the job of the next level.

Component integration testing

The test object is the interface between components: does one module pass the right data, in the right format, at the right time, to another? This level depends heavily on the integration strategy, which sets the order in which components are combined:

  • Bottom-up – start with lower-level components and work upwards, using drivers to call them.
  • Top-down – start with higher-level components and work downwards, using stubs for components not yet integrated.
  • Big-bang – integrate everything at once, which makes interface failures hard to localise.

Component integration testing comes before system testing in a sequential model, because the system's own components must work together before the system as a whole can be evaluated.

System testing and system integration testing

System testing evaluates the overall behaviour and capabilities of the whole system, while system integration testing evaluates the interfaces between that system and other systems or external services.

System testing

The test object is the entire system or product. System testing often includes functional testing of end-to-end tasks and non-functional testing of quality characteristics; some non-functional characteristics, such as usability, are best tested on the complete system in a representative test environment. Simulations of sub-systems can also be used. The test basis is the system's specifications, such as system requirements and use cases, and system testing may be performed by an independent test team.

System integration testing

The test object is the connection between the system under test and the outside world: an external SMS gateway, a partner's API, a downstream reporting system. Its test basis includes the agreed interface specifications. Because these interfaces behave differently in toy setups, system integration testing needs suitable test environments, preferably similar to the operational environment.

Component integration testingSystem integration testing
Looks atInterfaces between components inside one systemInterfaces between the system and other systems and external services
Typical exampleA library system's loan module passes member IDs to its fines moduleThe library system sends overdue notices through an external SMS gateway
Key dependencyThe integration strategy (bottom-up, top-down, big-bang)A test environment as close as possible to operations
Usual timingBefore system testingOnce the system itself is integrated (often alongside or after system testing)

Acceptance testing and its forms

Acceptance testing focuses on validation and on demonstrating readiness for deployment, which means showing that the system fulfils the users' business needs. Ideally it is performed by the intended users.

The difference from system testing is the question asked. System testing asks whether the system meets its specifications (verification), and it covers both functional and non-functional behaviour. Acceptance testing asks whether this is the right system for the people who will use and run it, and whether it can go live. It is not "the non-functional level": both levels can include non-functional testing.

The syllabus lists the main forms of acceptance testing (it groups contractual and regulatory acceptance testing together):

FormQuestion it answersTypical focus
User acceptance testing (UAT)Can the users do their work with it?Business users, checking fitness for their tasks and business processes
Operational acceptance testing (OAT)Can operations run and support it?System administrators and operations staff: installation, backup and restore, disaster recovery, user management, maintenance tasks, data loading and migration
Contractual acceptance testingDoes it meet the acceptance criteria in the contract?Checking against acceptance criteria agreed in a contract (for example with a supplier who built custom software)
Regulatory acceptance testingDoes it conform to the regulations it must follow?Checking conformance with government, legal or safety regulations
Alpha testingHow do (potential) users react before release?Users or customers testing a pre-release version at the developer's site
Beta testingHow does it behave in real use before general release?Selected users or customers testing a pre-release version at their own locations

Alpha and beta are the closest twins: both gather early feedback from users on pre-release software, and the deciding difference is where the testing happens.

How the five test levels compare

Each level differs in test object, typical test basis and who usually does the work, which is the quickest way to classify a scenario.

LevelTest objectTypical test basisUsually done by
ComponentOne component in isolationDetailed design, code, component specificationsDevelopers, in their development environment
Component integrationInterfaces and interactions between componentsSoftware and system design, interface definitions within the systemNot named in the syllabus; in practice often developers, following an integration strategy
SystemThe whole system, end to endSystem requirements specifications, use casesOften an independent test team
System integrationInterfaces with other systems and external servicesInterface specifications agreed with other systemsTesters, in an operational-like environment
AcceptanceThe system as it will be deployed and usedBusiness processes, user requirements, contracts, regulationsIdeally the intended users (and operations staff for OAT)

To classify a scenario, start with the test object (one isolated component, an interface inside the system, the whole system, an interface to another system, or the system's fitness for its users and operators), then check that the test basis and the people involved fit the same level.

What are test types? Functional and non-functional testing

A test type is a group of test activities aimed at a particular quality characteristic or test basis, and the CTFL syllabus names four: functional, non-functional, black-box and white-box testing. Functional and non-functional testing differ in what is evaluated.

Functional testing: what the system does

Functional testing evaluates the functions that a component or system should perform. Its main objective is to check three functional sub-characteristics:

  • Functional completeness – are all the specified functions present?
  • Functional correctness – do the functions give correct results?
  • Functional appropriateness – do the functions help users accomplish their specified tasks and objectives?

Non-functional testing: how well the system does it

Non-functional testing evaluates attributes other than functional characteristics. Its objective is to check the non-functional quality characteristics of the ISO/IEC 25010 product quality model, such as performance efficiency, compatibility, usability, reliability, security, maintainability and portability. (The 2023 revision of ISO/IEC 25010 renames usability as interaction capability and portability as flexibility, and adds safety; the ideas are the same.)

Four points about non-functional testing are worth knowing well:

  • Start early. It is sometimes appropriate for non-functional testing to start early in the lifecycle, for example as part of reviews and component testing. Late discovery of non-functional defects can pose a serious threat to a project's success, so leaving it all to the last week before release is a risk, not a plan.
  • Derived from functional tests. Many non-functional tests reuse functional tests and add a constraint: perform the function and check it completes within a specified time.
  • Special environments. Some non-functional testing needs a very specific environment, such as a usability lab for usability testing.
  • Not tied to one level. It is not reserved for acceptance testing, end users or production.
CheckTypeWhy
A hotel booking confirms the selected room and datesFunctionalCorrect result: what it does
The booking page loads within three seconds for 500 simultaneous guestsNon-functionalPerformance efficiency: how well it does it

Black-box and white-box testing

Black-box and white-box testing differ in where the tests come from: black-box tests are derived from documentation external to the test object, and white-box tests are derived from its internal structure.

Black-box testingWhite-box testing
Also calledSpecification-basedStructure-based
Test basisDocumentation external to the test object: requirements, specifications, user storiesThe implementation or internal structure: code, architecture, workflows, data flows
Main objectiveCheck the system's behaviour against its specificationsCover the underlying structure with tests to an acceptable level

"Structure" is wider than code. A tester at system level who designs tests to cover every interface in the architecture diagram, every step of a business workflow or every data flow between subsystems is doing white-box testing, because the tests come from structure and aim at coverage. Equally, black-box testing is not limited to the higher levels: a developer can derive component tests from the component's specification.

Tests based on the tester's knowledge of past defects and likely failure areas are a third category, experience-based testing, covered with test techniques in a later domain.

Can every test type be used at every test level?

Yes. All four test types can be applied at all test levels, although the focus differs at each level, and different test techniques can be used to derive test conditions and test cases for each type.

Treat levels and types as two independent dimensions: the level says at what stage and on what object you test, the type says which characteristic or basis you test against. Every combination is possible:

LevelFunctionalNon-functionalWhite-box
ComponentA date routine returns the correct loan due dateA sorting routine meets its time limit on large inputsUnit tests cover every branch of the late-fee calculation
System integrationAn overdue notice reaches the SMS gateway with the member's name and due dateThe gateway accepts a full night's batch of notices without lossTests cover every data flow between the library system and the gateway shown in the architecture
AcceptanceUsers complete an end-to-end claimUsability with real users in a usability labTests cover every path of the business workflow model

When asked to classify a test that combines both, identify the level from the test object, then the type from the basis or characteristic, and check that both hold.

Confirmation testing vs regression testing

Confirmation testing checks that an original defect has been successfully fixed; regression testing checks that a change, including that fix, has caused no adverse consequences. Both are change-related testing, and both are needed at every test level where defects are fixed or changes are made.

Confirmation testingRegression testing
QuestionIs the original defect gone?Did the change break anything else?
TriggerA defect fixAny change: a fix, new or changed code, or a change to the environment
What is testedThe fixed defect and the code changed to fix itThe same component, other components of the system, connected systems, and the environment
Tests usedPreviously failed test cases, new tests for the changes, or (if short of time) just the reproduction stepsA regression suite whose extent is optimised by impact analysis

Ways to do confirmation testing

Depending on risk, a fixed version can be tested by executing all test cases that previously failed because of the defect, and also by adding new tests to cover any changes made to fix it. When time or money for fixing defects is short, confirmation testing can be restricted to simply exercising the steps that should reproduce the failure and checking that it no longer occurs.

Scope of regression testing

Adverse consequences of a change can affect the component that was changed, other components in the same system, or even other connected systems. Regression testing is not restricted to the test object either: a change to the environment (a new application server, operating system or database version) calls for regression testing even when the application code is unchanged. Confirmation testing does not fit that case, because there is no fixed defect to confirm.

Impact analysis first

Before regression testing, it is advisable to perform an impact analysis to optimise its extent. Impact analysis shows which parts of the software, and which connected systems, could be affected by the change, so the team runs the regression tests that matter: wider than the changed module alone, narrower than the whole suite by default.

Automation and continuous integration

Regression test suites are run many times, and the number of regression test cases generally grows with each iteration or release, so regression testing is a strong candidate for automation, which should start early in the project. Where continuous integration is used, as in DevOps, it is good practice to include automated regression tests, possibly at several test levels.

Applying confirmation and regression testing together after a fix

After a defect fix, the two types are used together: confirmation testing first checks the fix, then regression testing checks for side effects of that fix. A fix that has passed confirmation testing still needs regression testing, because fixing one defect can introduce another.

A typical sequence after a defect in a shared component is fixed:

  1. Confirm the fix – re-run the failed test (at the level where the failure was found), add tests for the changed code where risk justifies it, or, if time is short, at least repeat the reproduction steps.
  2. Analyse the impact – identify the other components and connected systems that use the changed component.
  3. Run regression tests on the areas the analysis selects, including connected systems, not just the changed component.

Keep the two jobs apart. A regression suite is chosen to detect side effects, so it may never exercise the original defect; showing that the defect is gone is the job of confirmation testing. The reach of regression testing follows the impact of the change, which can extend to every system that consumes the changed component's output.

Changes that arise after a system is in operation, and how maintenance testing scopes them, are covered in the maintenance testing lesson.

Tip. Expect short K2 items that describe a test and ask which level, acceptance form or test type it is, plus statements to judge as true or false. Level questions turn on the test object, test basis and who performs the testing, so learn the attributes that separate the twins: component vs component integration, component integration vs system integration, and system vs acceptance. Acceptance items name the testers and focus (users, operations staff, contract, regulation, developer's site or customers' sites). Test-type items check what versus how well, external specification versus internal structure, and the rule that every type applies at every level. Harder items combine two facts, such as a test type at a given level or confirmation and regression testing after a fix with time pressure, connected systems or an environment change.

Key takeaways
  • There are five test levels: component, component integration, system, system integration and acceptance; each is an instance of the same test process.
  • Levels are distinguished by test object, objectives, test basis, defects and failures, and approach and responsibilities, not by quality characteristic.
  • In sequential models one level's exit criteria often feed the next level's entry criteria; in iterative models levels can overlap.
  • Component testing isolates a component with harnesses, frameworks and stubs and is normally done by developers in their own environment.
  • Component integration testing looks at interfaces inside one system and depends on the integration strategy; system integration testing looks at interfaces with other systems in an operational-like environment.
  • Acceptance testing validates business needs and readiness for deployment, ideally by intended users; its forms are UAT, OAT, contractual, regulatory, alpha (developer's site) and beta (users' own sites).
  • Functional testing checks what the system does (completeness, correctness, appropriateness); non-functional testing checks how well, should start early and may need special environments such as a usability lab.
  • Black-box tests come from external specifications; white-box tests come from internal structure (code, architecture, workflows, data flows) and aim at coverage.
  • All four test types can be applied at all test levels, with a different focus at each.
  • Confirmation testing checks the original defect is fixed; regression testing checks a change caused no adverse effects anywhere, including connected systems and the environment, after an impact analysis.

Frequently asked questions

What are the five test levels in ISTQB CTFL?

The CTFL v4.0.1 syllabus names five test levels: component (unit) testing, component integration testing, system testing, system integration testing and acceptance testing. Each is an instance of the test process, and they are distinguished by test object, test objectives, test basis, typical defects and failures, and approach and responsibilities.

What is the difference between component integration testing and system integration testing?

Component integration testing checks the interfaces and interactions between components inside one system and depends on an integration strategy such as bottom-up, top-down or big-bang. System integration testing checks the interfaces between the system under test and other systems or external services, and it needs a test environment as close as possible to the operational one.

How is acceptance testing different from system testing?

System testing evaluates the whole system's functional and non-functional behaviour against its specifications and is often done by an independent test team. Acceptance testing validates that the system meets users' business needs and is ready for deployment, and it is ideally performed by the intended users.

What is the difference between alpha testing and beta testing?

Both are forms of acceptance testing in which users or customers try a pre-release version and report problems. Alpha testing takes place at the developing organisation's site, while beta testing takes place at the users' or customers' own locations.

What are the four test types in the CTFL syllabus?

The four test types are functional testing (what the system does), non-functional testing (how well it does it, using ISO/IEC 25010 characteristics), black-box testing (tests derived from external specifications) and white-box testing (tests derived from internal structure such as code, architecture, workflows and data flows). All four can be applied at every test level.

Is white-box testing only done at component level?

No. White-box testing derives tests from structure with the aim of covering it, and structure includes architecture, workflows and data flows as well as code. Covering every interface or data flow of a system during system or integration testing is white-box testing at a higher level.

What is the difference between confirmation testing and regression testing?

Confirmation testing checks that the original defect has been fixed, for example by re-running the tests that failed or, when time is short, repeating the steps that reproduced the failure. Regression testing checks that a change, including a fix, has caused no adverse consequences in the same component, other components, connected systems or the environment.

Why is impact analysis done before regression testing?

Impact analysis identifies which parts of the software and which connected systems a change could affect. Doing it before regression testing optimises the extent of the regression tests, so the team covers the areas at risk instead of only the changed module or, by default, the entire suite.

Source

This lesson covers the "Testing Throughout the Software Development Lifecycle" domain of the official CTFL exam guide. Vendors revise their guides — check the source for the current version.

Sign up free to mark lessons complete, bookmark topics and track your exam readiness.

Spotted a mistake in this lesson?